Major setback for California's high speed train

The future of the California high speed rail project hangs in the balance as a result of two rulings handed down by Sacramento Superior Court Judge Michael Kenny on 25 November. "The judge's ruling will prevent the [California High-Speed Rail] Authority from spending bond measure funds for construction until the funding plan is brought into compliance," said Michael Brady, co- lead attorney on the case, but because that would require finding at least US$25 billion in extra funds, Brady believes complianc
November 28, 2013 Read time: 2 mins
The future of the California high speed rail project hangs in the balance as a result of two rulings handed down by Sacramento Superior Court Judge Michael Kenny on 25 November.

"The judge's ruling will prevent the [California High-Speed Rail] Authority from spending bond measure funds for construction until the funding plan is brought into compliance," said Michael Brady, co- lead attorney on the case, but because that would require finding at least US$25 billion in extra funds, Brady believes compliance seems "virtually impossible." They need to step back and rethink their whole approach," added co-lead attorney Stuart Flashman.

The Authority’s Chairman, Dan Richard, tried to cast the court decision in a more positive light. "The judge did not invalidate the bonds as approved by the voters," he said. "Like all transformative projects, we understand that there will be many challenges that will be addressed as we go forward in building the nation’s first high-speed rail system."

The court rulings are the culmination of prolonged litigation that began two years ago when Kings County Board of Supervisors filed a lawsuit asserting that the Authority failed to comply with certain statutory requirements in its 2011 funding plan.

In his 25 November opinion, Judge Kenny did not explicitly address this potential funding deficiency nor did he agree to rescind existing contracts with Tutor-Perini and 3879 Caltrans or rule on the propriety of using federal grant money, as requested by the plaintiffs.

Instead, he ruled that the Authority cannot "proceed to commit and spend Proposition 1A bond proceeds for construction or property acquisition" until it has complied with the requirements stated in his 16 August ruling, when he ruled that the Authority failed to comply with the requirements of Proposition 1A in two fundamental respects:  It was unable to certify completion of all the environmental clearances for the 300-mile Initial operating segment (IOS) extending from Merced to San Fernando Valley; and it was unable to identify "reasonably expected" sources of funds required to complete the Initial operating segment.

Related Content

  • August 1, 2014
    US Senate approves Highway Trust Fund patch
    The US Congress gave final approval last night to a US$10.8 billion bill to replenish the federal Highway Trust Fund and through to May 2015. It now goes to President Barack Obama for his signature. The Transportation Department had set Friday as the day the Highway Trust Fund would run out of reserves and told states they could expect an average 28 percent reduction in federal aid. The fund relies primarily on gasoline and diesel fuel taxes that haven’t been increase in two decades. Commenting on the
  • June 20, 2012
    Multi-modal transport system key to liveable city development
    Malaysia’s Economic Transformation Programme aims to transform Kuala Lumpur into one of the world’s most liveable cities. Mohd Nur Kamal, CEO of SPAD, Malaysia’s Land Transport Commission, explains how a world class multi-modal transport system will be key to reaching that goal Superficially, Kuala Lumpur, or KL as it is commonly known, is the model of a vibrant, modern, cosmopolitan city to equal any in the world. The Petronas Twin Towers, an iconic global symbol of Malaysia, are surrounded by stunningly
  • March 12, 2012
    Vendor's eye view of US economic stimulus programme
    Pete Goldin explores the impact of the US economic stimulus programme on the ITS industry from the ITS vendor perspective
  • September 11, 2014
    Gatso to participate in German average speed pilot
    The idea of average speed enforcement, or section control, in Germany has long been discussed by German authorities following its recommendation in 2009 by the 47th German Traffic Court Day. Interior Minister Boris Pistorius has announced a section control pilot project which is scheduled to be operational in Lower Saxony in spring 2015. Instead measuring speed in the conventional at a single point, section control measures average speed over a longer stretch of road. This method usually results in l