Major setback for California's high speed train

The future of the California high speed rail project hangs in the balance as a result of two rulings handed down by Sacramento Superior Court Judge Michael Kenny on 25 November. "The judge's ruling will prevent the [California High-Speed Rail] Authority from spending bond measure funds for construction until the funding plan is brought into compliance," said Michael Brady, co- lead attorney on the case, but because that would require finding at least US$25 billion in extra funds, Brady believes complianc
November 28, 2013 Read time: 2 mins
The future of the California high speed rail project hangs in the balance as a result of two rulings handed down by Sacramento Superior Court Judge Michael Kenny on 25 November.

"The judge's ruling will prevent the [California High-Speed Rail] Authority from spending bond measure funds for construction until the funding plan is brought into compliance," said Michael Brady, co- lead attorney on the case, but because that would require finding at least US$25 billion in extra funds, Brady believes compliance seems "virtually impossible." They need to step back and rethink their whole approach," added co-lead attorney Stuart Flashman.

The Authority’s Chairman, Dan Richard, tried to cast the court decision in a more positive light. "The judge did not invalidate the bonds as approved by the voters," he said. "Like all transformative projects, we understand that there will be many challenges that will be addressed as we go forward in building the nation’s first high-speed rail system."

The court rulings are the culmination of prolonged litigation that began two years ago when Kings County Board of Supervisors filed a lawsuit asserting that the Authority failed to comply with certain statutory requirements in its 2011 funding plan.

In his 25 November opinion, Judge Kenny did not explicitly address this potential funding deficiency nor did he agree to rescind existing contracts with Tutor-Perini and 3879 Caltrans or rule on the propriety of using federal grant money, as requested by the plaintiffs.

Instead, he ruled that the Authority cannot "proceed to commit and spend Proposition 1A bond proceeds for construction or property acquisition" until it has complied with the requirements stated in his 16 August ruling, when he ruled that the Authority failed to comply with the requirements of Proposition 1A in two fundamental respects:  It was unable to certify completion of all the environmental clearances for the 300-mile Initial operating segment (IOS) extending from Merced to San Fernando Valley; and it was unable to identify "reasonably expected" sources of funds required to complete the Initial operating segment.

Related Content

  • September 5, 2013
    Drivers with up to 42 points still on the road
    New figures from the UK Driver and Vehicle Licensing Agency (DVLA) have revealed that motorists with up to 42 penalty points on their licence are still driving on Britain’s roads. Drivers can be banned from the road if they accumulate 12 points on their licence over a three-year period, but there are 8,000 drivers still getting behind the wheel despite having reached or exceeded that number.
  • December 3, 2018
    Public transit is weapon in US congestion war
    Public transit is a huge component of US transportation, insists Mary Scott Nabers, CEO of Strategic Partnerships – and infrastructure upgrades have the potential to create thousands of jobs When it comes to public transportation, the US lags far behind other countries. Governments in Europe, Asia and Canada invest heavily in public transportation because it is viewed as an essential public good. The US government, however, views public transit a little differently and funding has been inadequate for d
  • April 16, 2018
    MaaS is at the ‘baby steps’ stage – but needs to get up and running soon
    Data sharing between organisations remains a potential problem for Mobility as a Service projects, attendees at February's MaaS Market conference in London were told. Alan Dron listens in on the presentations.
  • November 21, 2012
    Transportation hub the centre of sustainable urban development
    A marriage of transit, technology and culture is taking shape in Minneapolis, with ITS systems vital to hopes for a sustainable development centred on a hub of public transportation. Construction started in July this year on ‘The Interchange’ – a station in the Midwest US city of Minneapolis claimed as the most spectacular expression yet of the fast-spreading North American concept of transit-oriented development (TOD). Due for completion in 2014, the Interchange is designed as a multi-modal public transpor