‘Formation flying’ engineering trains used to upgrade railway

In a bid to increase efficiencies and reduce delays for passengers, the UK’s Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete. The pioneering technique was used successfully at Sandy, Bedfordshire, on
February 16, 2017 Read time: 2 mins
In a bid to increase efficiencies and reduce delays for passengers, the UK’s 5021 Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete.

The pioneering technique was used successfully at Sandy, Bedfordshire, on a set of railway switches and crossings, which were being replaced as part of the Railway Upgrade Plan.

A pair of engineering trains were joined together connected by an umbilical and ran in parallel to simultaneously deliver tamping and dynamic track stabilisation (DTS) which simulated the equivalent of 200 trains passing over the tracks consecutively. Passenger trains were then able to start using the railway at speeds as high as 125mph as soon as the engineering team had finished because the track and ballast were firmly ‘bedded in’ – which meant Network Rail avoided thousands of pounds in compensation payments.

The news comes almost one year after Network Rail’s first successes with 125mph ‘high speed handbacks’ in January 2016 on regular plain line track. High speed handback ensures track is installed at each stage to its specific design tolerances, that care is taken while tamping to get the track to its final exact co-ordinates and that welding and stressing is completed as part of the core works.

Network Rail estimates that over US$6.2 million (£5 million) has already been saved by avoiding compensation payments since the start of the high speed handback programme.

Related Content

  • September 5, 2014
    Chile needs major smart city investment
    Chile needs to invest US$30 billion in telecom infrastructure over the next ten years to boost its potential to develop smart cities, according to Pelayo Covarrubias, board president of digital development organisation País Digital. During a seminar on smart cities, Covarrubias said Chile had invested US$15 billion in telecom infrastructure in the last decade. The estimated investment for the next decade is the minimum Chile would need to spend just to be able to keep up with other high-ranking digital citi
  • March 11, 2015
    Keeping a watching brief over traffic flows
    Monitoring traffic flows is set to become an even bigger challengebut a revolution in camera technology can help, as Patrik Anderson explains. By 2025 almost 60% of the world’s population will live in urban areas and in those cities there will be an estimated 6.2 billion private motorised trips every day. In order to manage this level of traffic growth, traffic management centres (TMCs) will need to both increase their monitoring capabilities and be able to detect traffic problems quickly, efficiently and r
  • August 12, 2015
    Figures show Express Lanes bring wider benefits
    Drivers in the Washington DC area are realising time savings following the opening of Express Lanes on the I-95 - and not only those paying to use the new facility. Washington is ranked as being the worst gridlocked city in the United States. Every day its drivers face an average commute time of 39.5 minutes and they waste an average of 67 hours every year just sitting in traffic. In a move to counter these problems, late last December new Express Lanes were opened along 46.6km (29 miles) of the I-95 betwee
  • March 18, 2014
    Kenya WIM system cuts four days off journey times
    Shem Oirere looks at how weigh-in-motion is helping to streamline the trucking industry in Kenya. Kenya, East Africa’s largest economy, is streamlining trucking operations on its section of the 8,800km Northern Corridor. It is both reducing the number of weighbridges and automating the remaining ones in an effort to improve efficiency and eliminate corruption.The Northern Corridor is a major gateway through Kenya to the landlocked countries of Uganda, Rwanda, Burundi, Democratic Republic of Congo and Sou