‘Formation flying’ engineering trains used to upgrade railway

In a bid to increase efficiencies and reduce delays for passengers, the UK’s Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete. The pioneering technique was used successfully at Sandy, Bedfordshire, on
February 16, 2017 Read time: 2 mins
In a bid to increase efficiencies and reduce delays for passengers, the UK’s 5021 Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete.

The pioneering technique was used successfully at Sandy, Bedfordshire, on a set of railway switches and crossings, which were being replaced as part of the Railway Upgrade Plan.

A pair of engineering trains were joined together connected by an umbilical and ran in parallel to simultaneously deliver tamping and dynamic track stabilisation (DTS) which simulated the equivalent of 200 trains passing over the tracks consecutively. Passenger trains were then able to start using the railway at speeds as high as 125mph as soon as the engineering team had finished because the track and ballast were firmly ‘bedded in’ – which meant Network Rail avoided thousands of pounds in compensation payments.

The news comes almost one year after Network Rail’s first successes with 125mph ‘high speed handbacks’ in January 2016 on regular plain line track. High speed handback ensures track is installed at each stage to its specific design tolerances, that care is taken while tamping to get the track to its final exact co-ordinates and that welding and stressing is completed as part of the core works.

Network Rail estimates that over US$6.2 million (£5 million) has already been saved by avoiding compensation payments since the start of the high speed handback programme.

Related Content

  • April 20, 2017
    Strabag to modernise Polish railway
    Construction group Strabag, as part of a consortium including Krakowskie Zakłady Automatyki, is to modernise the 20 km long section of rail between Cracow and Rudzice and expand the suburban railway in Cracow. The project includes the construction of a new metropolitan rail line to serve Cracow’s suburbs, which will see new track and stations built and existing ones e modernised. A total of 55 bridges are to be erected, including two rail bridges over the river Vistula with a length of 234 m and 227 m. The
  • February 1, 2012
    No in-road equipment for Queensland's free flow toll bridge
    By May this year, the new Gateway Bridge in Brisbane, which is being built alongside an existing bridge, will be open. With it will come an end-to-end free-flow tolling system. Interview with Sue Caelers, Queensland Motorway Ltd. Queensland Motorways Ltd owns and operates 61km of roadway in the area around Brisbane, Australia. This includes the Gateway Bridge and the Gateway Extension, Logan and Port of Brisbane motorways.
  • August 23, 2016
    UK university projects shows wireless sensors could improve rail crossing safety
    A study by rail experts at the University of Huddersfield in the UK has concluded that railway crossing safety could be improved by networks of tiny wireless sensors attached to the tracks. Following extensive research at the university’s Institute of Railway Research (IRR), the Department for Transport-funded project established that the sensors could be powered by vibrations from approaching trains. They would then form a wireless network to send a message to lower or raise the gates. According to t
  • June 6, 2014
    Glasgow’s new Operations Centre has a key role in city’s future
    David Crawford investigates a control centre with a future. Destined to play a central role in keeping the city and its transport running smoothly during the 2014 Commonwealth Games in July, the new Glasgow Operations Centre in Scotland’s largest urban centre formally went live earlier this year. The aim was to dry run its far-reaching integration of previously distinct core systems and familiarise the public with the initial phase of what will be a long-term post-event legacy. The centre brings together, i