‘Formation flying’ engineering trains used to upgrade railway

In a bid to increase efficiencies and reduce delays for passengers, the UK’s Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete. The pioneering technique was used successfully at Sandy, Bedfordshire, on
February 16, 2017 Read time: 2 mins
In a bid to increase efficiencies and reduce delays for passengers, the UK’s 5021 Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete.

The pioneering technique was used successfully at Sandy, Bedfordshire, on a set of railway switches and crossings, which were being replaced as part of the Railway Upgrade Plan.

A pair of engineering trains were joined together connected by an umbilical and ran in parallel to simultaneously deliver tamping and dynamic track stabilisation (DTS) which simulated the equivalent of 200 trains passing over the tracks consecutively. Passenger trains were then able to start using the railway at speeds as high as 125mph as soon as the engineering team had finished because the track and ballast were firmly ‘bedded in’ – which meant Network Rail avoided thousands of pounds in compensation payments.

The news comes almost one year after Network Rail’s first successes with 125mph ‘high speed handbacks’ in January 2016 on regular plain line track. High speed handback ensures track is installed at each stage to its specific design tolerances, that care is taken while tamping to get the track to its final exact co-ordinates and that welding and stressing is completed as part of the core works.

Network Rail estimates that over US$6.2 million (£5 million) has already been saved by avoiding compensation payments since the start of the high speed handback programme.

For more information on companies in this article

Related Content

  • 250,000 Efkon OBUs for Malaysia
    February 1, 2012
    Efkon Asia, the Kuala Lumpur-based subsidiary of Efkon AG, Austria, has received an additional order for 250,000 mult-lane free flow On Board Units (two piece OBU with integrated contactless Mifare Smart Card) based on high speed bi-directional active ISO CALM compatible Infrared.
  • Small toll agency adopts big city thinking
    December 5, 2014
    Andrew Bardin Williams looks at a novel option for new toll road authorities. While somewhat politically controversial, outsourcing has gained traction in the business world as a model worth investigating for its efficiency and cost saving benefits. Lean start-ups tend to employ independent contractors instead of full-time employees in an effort to remain flexible and avoid costs associated with pensions, retirement places, health insurance, office space and benefit packages.
  • Sice systems future proof Fehmarnbelt Tunnel
    April 4, 2023
    Picking up the electro-mechanical contract for the Fehmarnbelt Tunnel was a milestone, according to David Calero Monteagudo, head of global ITS and tunnel business for Spanish company Sice. David Arminas finds out more
  • Two seconds – the difference between life and death
    October 17, 2016
    Professor Donald Fisher has spent 15 years identifying factors that increase the crash risk of novice and older drivers. His findings highlight the difference between living and dying, Colin Sowman reports.