‘Formation flying’ engineering trains used to upgrade railway

In a bid to increase efficiencies and reduce delays for passengers, the UK’s Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete. The pioneering technique was used successfully at Sandy, Bedfordshire, on
February 16, 2017 Read time: 2 mins
In a bid to increase efficiencies and reduce delays for passengers, the UK’s 5021 Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete.

The pioneering technique was used successfully at Sandy, Bedfordshire, on a set of railway switches and crossings, which were being replaced as part of the Railway Upgrade Plan.

A pair of engineering trains were joined together connected by an umbilical and ran in parallel to simultaneously deliver tamping and dynamic track stabilisation (DTS) which simulated the equivalent of 200 trains passing over the tracks consecutively. Passenger trains were then able to start using the railway at speeds as high as 125mph as soon as the engineering team had finished because the track and ballast were firmly ‘bedded in’ – which meant Network Rail avoided thousands of pounds in compensation payments.

The news comes almost one year after Network Rail’s first successes with 125mph ‘high speed handbacks’ in January 2016 on regular plain line track. High speed handback ensures track is installed at each stage to its specific design tolerances, that care is taken while tamping to get the track to its final exact co-ordinates and that welding and stressing is completed as part of the core works.

Network Rail estimates that over US$6.2 million (£5 million) has already been saved by avoiding compensation payments since the start of the high speed handback programme.

For more information on companies in this article

Related Content

  • Atlanta slows down to 25mph
    May 6, 2020
    The city will soon start putting up around 1,000 signs notifying the 25mph limit
  • Freight poses growing problem for city authorities
    March 3, 2017
    Wes Guckert considers possible solutions and countermeasures to the problems of increased freight deliveries in growing cities. In January 2016, the US Department of Transportation (USDoT) conducted a session on the SmartCity Challenge and Urban Freight and Logistics. This session was a follow-up to the USDoT report titled, Beyond Traffic 2045.
  • BlipTrack monitoring in New Zealand
    January 24, 2013
    Danish wireless technology company Blip systems has supplied engineering and technology services provider Beca with its BlipTrack Bluetooth traffic monitoring system, which has been deployed in Waikato, New Zealand. The Te Rapa Bypass project is the first of a planned US$2 billion investment by the New Zealand Transport Agency (NZTA) in the Waikato region’s transportation network over the next eight years. The BlipTrack solution has been established in advance of these projects and will continue to assess
  • Caltrans trials Xerox’s Passenger Detection System
    October 30, 2015
    Xerox’s Passenger Detection System has been trialled in California and compared with the state’s team of human counters giving some interesting results, as Colin Sowman discovers. Like others adopting high-occupancy and high-occupancy vehicle (HOV) lanes for congestion management, Caltrans has faced challenges with compliance in what has been effectively an ‘honour system’ with drivers trusted to set their tags correctly or comply with the multi-passenger requirement.