Skip to main content

Consortium named for Pennsylvania PPP bridge project

A consortium comprising HDR, Plenary Group, Walsh Group and Granite Construction Company has been awarded the contract to replace 558 bridges as part of the Pennsylvania Rapid Bridge Replacement Project in the US. As lead design engineer for the construction joint venture, HDR will be responsible for bridge and roadway design services, environmental permits, right-of-way plan development and construction phase services. The team will begin construction in summer 2015 and complete all bridge replaceme
January 27, 2015 Read time: 1 min
A consortium comprising 59 HDR, 7975 Plenary Group, 7974 Walsh Group and 7973 Granite Construction Company has been awarded the contract to replace 558 bridges as part of the Pennsylvania Rapid Bridge Replacement Project in the US.

As lead design engineer for the construction joint venture, HDR will be responsible for bridge and roadway design services, environmental permits, right-of-way plan development and construction phase services.

The team will begin construction in summer 2015 and complete all bridge replacements by year-end 2017. The commonwealth will retain ownership of the bridges but the team will be responsible for maintaining each bridge for 25 years.

For more information on companies in this article

Related Content

  • Italian consortium to build Naples-Bari high-speed railway
    March 2, 2017
    A consortium of Salini Impregilo and Astaldi has won a contract valued at US$418 million (€397 million) for the design and construction of the Naples to Cancello section of the Naples to Bari high-speed railway line in Italy, part of the Scandinavia to Mediterranean Corridor of the Trans-European Network (TEN).
  • Mobile LiDAR technology used to capture traffic signal data across Pennsylvania
    November 30, 2016
    Engineering, planning and consulting services company Michael Baker International recently completed a nearly US$7-million project for the Pennsylvania Department of Transportation (PennDOT) to collect data from more than 8,600 traffic signals across the state. Over a year, the Michael Baker team, working with PennDOT’s Traffic Signal Asset Management System (TSAMS), collected nearly 20 million data fields for each of the 8,623 traffic signals analysed, which populated a centralised database to support Pen
  • Øresund bridges the front line for border crossing traffic
    September 15, 2016
    Timothy Compston considers the challenges faced by the operators of the Øresund Bridge between Denmark and Sweden, the largest structure of its kind across Europe. In light of the concerns about the ongoing security threat and the unprecedented flow of migrants, many of the countries that make up the Schengen Area in Europe have re-introduced border controls. For its part, Sweden has rolled out ID checks for train, bus and ferry passengers from Denmark placing the landmark Øresund Bridge very much on the fr
  • Environmental impact assessments - where now?
    February 1, 2012
    Peter George, MVA Consultancy, questions the future direction of environmental impact assessments