Signal optimisation reduces congestion, improves travel times

The Metropolitan Government of Nashville and Davidson County's Department of Public Works(MPW) identified seven corridors in the County that experience heavy traffic congestion and needed traffic signal timing improvements to improve traffic flow as well as air quality and fuel consumption. The seven corridors included a total of 223 signalised intersections. To conduct this study, termed the Traffic Signal Optimisation Study for the Metro Nashville Signal System, MPW received funding from the Federal Conge
February 2, 2012 Read time: 4 mins
RSSThe 2141 Metropolitan Government of Nashville and Davidson County's Department of Public Works(MPW) identified seven corridors in the County that experience heavy traffic congestion and needed traffic signal timing improvements to improve traffic flow as well as air quality and fuel consumption. The seven corridors included a total of 223 signalised intersections. To conduct this study, termed the Traffic Signal Optimisation Study for the Metro Nashville Signal System, MPW received funding from the Federal Congestion Mitigation and Air Quality (CMAQ) Program via the 2142 Nashville Area Metropolitan Planning Organisation (MPO).

The consultant team MPW selected to conduct this study was 422 Kimley-Horn and Associates, with Stammer Transportation Engineering, and Bowlby & Associates as part of the team. The project scope included significant data collection efforts, an assessment of existing Project:
• Traffic signal optimisation, Metro Nashville, Tennessee, US

Cost:
• $750,000 (Phase I)
ROI:
• $14,770,900 first year (21:1)
•$46,326,550 over three years (62:1)

Benefits:
•Reduction in traffic congestion for Davidson County motorists
• Environmental improvements - reduction in fuel consumption
conditions, identification of potential improvements, the development of timing plans for each period of the day including weekdays and weekend, and field implementation of the proposed timing plans. In addition, the project included the development of MPW's Traffic Signal Timing and Phasing Policy, development and presentation of a two-part training programme for MPW staff, travel time and delay studies, air quality analyses and complete project documentation.

Benefits

Results from the signal timing effort included a 20 per cent reduction in delay for the seven corridors, with the greatest delay reduction of approximately 37 per cent along the Nolensville Pike and Harding Place corridors. Benefits in reduced fuel consumption also were realised with this project. A reduction of nearly six per cent in fuel consumption along the seven corridors was achieved. Furthermore, improvements in air quality were achieved. Volatile organic compounds were reduced by 3 per cent, nitrogen oxides by approximately 1 per cent, and carbon monoxide by nearly 1 per cent.

Economic analysis

Based on the results from the delay study, fuel consumption analysis, and the air quality analysis, an economic evaluation was conducted for the project to determine what benefits arose from the implementation of the new signal timing plans. The benefits studied included reduced road user costs from reduced delay experienced by the motoring public, air pollutants and fuel consumption. To determine these economic benefits, Kimley-Horn studied the AM, midday, and PM peak periods of the weekdays. Therefore, economic benefits were not quantified for the non-peak hours of the day and are not reflected in this analysis.

To calculate the cost savings resulting in the reduction of delay by the motoring public, a dollar value was assigned to the delay. The 324 US Department of Transportation provides data for this purpose. Using this data, analyses were made for each corridor in the project, and these results were tallied to yield a benefit in terms of reduced delay for the entire project. For a one-year period this benefit was calculated to be $14,770,900.

Economic benefits also were realised for the reduced emissions that resulted from the improved signal timing plans. This was calculated by assigning a cost to each of Economic analysis the three pollutants, as documented by the Federal Highways Administration. For the entire project over a one year period the benefit was found to be $33,655.

Similarly, the economic benefit was determined for the reduced fuel consumption. A conservative value of $2.00 per gallon of fuel was used for this analysis. For the whole project, this was found to be $637,630 for a one-year timeframe.

By using an engineering fee for this project, a benefit-to cost ratio was calculated. The benefits were the sum of the delay, emissions and fuel benefits over a one-year timeframe totaling $15,442,180. The cost was the contract value for the project: $750,000. This yielded a one year benefit-to-cost ratio of 21:1. However, the implemented signal timing plans will be used and prove to be beneficial for a time period longer than one year.

Typically the useful life for signal timing plans is three years, as recommended by the ITE ("At a minimum, an operating agency should budget to retime traffic signals at least every three years.") Therefore, the three-year benefit is $46,326,550, while the cost remains only $750,000. This yields a three-year benefit-to-cost ratio of 62:1.


RSS

Related Content

  • ITS-NY Announces 2012 Project of the Year Award Winners
    June 13, 2012
    The Intelligent Transportation Society of New York (ITS-NY) has announced the 2012 ITS-NY Project of the Year Winners at its Nineteenth Annual Meeting and Technology Exhibition in Saratoga Springs, NY. “These winning projects feature ITS and technologies at work in New York State to improve traveller mobility and safety, as well as the efficiency of New York State’s transportation system across all modes of travel,” said Dr Isaac Takyi, ITS-NY president. Winning Projects were announced in the following ITS
  • Big data analytics identifies congestion increases
    November 26, 2014
    Iteris has completed and published the Alameda County Transportation Commission (Alameda CTC) 2014 Level of Service Monitoring Report. The report was generated for speed-based congestion monitoring, utilising big data analytics in place of conventional in-field manual data collection for 205 miles of the 327 mile network. Use of big data analytics will be expanded in future monitoring cycles. Many agencies conduct congestion monitoring through manual data collection efforts. Agencies traditionally us
  • Parsons Brinckerhoff to evaluate Babylon transportation
    November 24, 2014
    Parsons Brinckerhoff has been awarded a contract by the Town of Babylon to conduct an Alternatives Analysis for Route 110 within the towns of Babylon and Huntington in Suffolk County, New York. The purpose of the study is to evaluate transportation demand in the Route 110 corridor, manage congestion, maximise environmental benefits and enhance economic competitiveness.
  • Bus lane enforcement reduces costs, journey times
    May 4, 2012
    The Southcote Lane site in the UK town of Reading is a notorious shortcut for motorists travelling into the town centre. The resultant congestion at the end of the bus lane, when motorists tried to re-enter the main traffic flow, caused congestion and disruption to bus timetables. Reading Borough Council wanted a cost-efficient, effective solution to accurately capture bus lane violations and improve bus travel times. Reading became the first local authority in the UK to deploy Siemens's LaneHawk fully auto