Skip to main content

Signal optimisation reduces congestion, improves travel times

The Metropolitan Government of Nashville and Davidson County's Department of Public Works(MPW) identified seven corridors in the County that experience heavy traffic congestion and needed traffic signal timing improvements to improve traffic flow as well as air quality and fuel consumption. The seven corridors included a total of 223 signalised intersections. To conduct this study, termed the Traffic Signal Optimisation Study for the Metro Nashville Signal System, MPW received funding from the Federal Conge
February 2, 2012 Read time: 4 mins
RSSThe 2141 Metropolitan Government of Nashville and Davidson County's Department of Public Works(MPW) identified seven corridors in the County that experience heavy traffic congestion and needed traffic signal timing improvements to improve traffic flow as well as air quality and fuel consumption. The seven corridors included a total of 223 signalised intersections. To conduct this study, termed the Traffic Signal Optimisation Study for the Metro Nashville Signal System, MPW received funding from the Federal Congestion Mitigation and Air Quality (CMAQ) Program via the 2142 Nashville Area Metropolitan Planning Organisation (MPO).

The consultant team MPW selected to conduct this study was 422 Kimley-Horn and Associates, with Stammer Transportation Engineering, and Bowlby & Associates as part of the team. The project scope included significant data collection efforts, an assessment of existing Project:
• Traffic signal optimisation, Metro Nashville, Tennessee, US

Cost:
• $750,000 (Phase I)
ROI:
• $14,770,900 first year (21:1)
•$46,326,550 over three years (62:1)

Benefits:
•Reduction in traffic congestion for Davidson County motorists
• Environmental improvements - reduction in fuel consumption
conditions, identification of potential improvements, the development of timing plans for each period of the day including weekdays and weekend, and field implementation of the proposed timing plans. In addition, the project included the development of MPW's Traffic Signal Timing and Phasing Policy, development and presentation of a two-part training programme for MPW staff, travel time and delay studies, air quality analyses and complete project documentation.

Benefits

Results from the signal timing effort included a 20 per cent reduction in delay for the seven corridors, with the greatest delay reduction of approximately 37 per cent along the Nolensville Pike and Harding Place corridors. Benefits in reduced fuel consumption also were realised with this project. A reduction of nearly six per cent in fuel consumption along the seven corridors was achieved. Furthermore, improvements in air quality were achieved. Volatile organic compounds were reduced by 3 per cent, nitrogen oxides by approximately 1 per cent, and carbon monoxide by nearly 1 per cent.

Economic analysis

Based on the results from the delay study, fuel consumption analysis, and the air quality analysis, an economic evaluation was conducted for the project to determine what benefits arose from the implementation of the new signal timing plans. The benefits studied included reduced road user costs from reduced delay experienced by the motoring public, air pollutants and fuel consumption. To determine these economic benefits, Kimley-Horn studied the AM, midday, and PM peak periods of the weekdays. Therefore, economic benefits were not quantified for the non-peak hours of the day and are not reflected in this analysis.

To calculate the cost savings resulting in the reduction of delay by the motoring public, a dollar value was assigned to the delay. The 324 US Department of Transportation provides data for this purpose. Using this data, analyses were made for each corridor in the project, and these results were tallied to yield a benefit in terms of reduced delay for the entire project. For a one-year period this benefit was calculated to be $14,770,900.

Economic benefits also were realised for the reduced emissions that resulted from the improved signal timing plans. This was calculated by assigning a cost to each of Economic analysis the three pollutants, as documented by the Federal Highways Administration. For the entire project over a one year period the benefit was found to be $33,655.

Similarly, the economic benefit was determined for the reduced fuel consumption. A conservative value of $2.00 per gallon of fuel was used for this analysis. For the whole project, this was found to be $637,630 for a one-year timeframe.

By using an engineering fee for this project, a benefit-to cost ratio was calculated. The benefits were the sum of the delay, emissions and fuel benefits over a one-year timeframe totaling $15,442,180. The cost was the contract value for the project: $750,000. This yielded a one year benefit-to-cost ratio of 21:1. However, the implemented signal timing plans will be used and prove to be beneficial for a time period longer than one year.

Typically the useful life for signal timing plans is three years, as recommended by the ITE ("At a minimum, an operating agency should budget to retime traffic signals at least every three years.") Therefore, the three-year benefit is $46,326,550, while the cost remains only $750,000. This yields a three-year benefit-to-cost ratio of 62:1.


RSS

Related Content

  • Emissions reductions targets to have major impact on transport
    October 28, 2015
    As bold moves aimed at reducing greenhouse gas emissions have been introduced in California, David Crawford looks at the ramifications for transportation. California Governor Jerry Brown’s recent dramatic raising of the bar on emissions reduction policy for the state has won him praise from Japan, Australia, Europe and the secretariat of the critical UN conference on climate change being held in Paris in November/December 2015. His April 2015 executive order aimed at bringing emissions to 40% below 1990 lev
  • Cut freight deliveries – improve Southampton’s air quality
    November 23, 2018
    Taking the pressure off cities’ road networks can have a beneficial effect on the environment. David Crawford looks at a new economic model which seeks to quantify the societal effect of freight traffic in Southampton, one of the UK’s five most polluted cities Cuts of 60% or more in volumes of freight deliveries are being predicted - along with badly-needed improvements in air quality - from a load consolidation scheme currently being introduced in the UK port city of Southampton. The forecasts are based o
  • Peer-to-peer car sharing expected to become the next big thing in the market
    October 22, 2013
    Frost & Sullivan’s recent customer research study on car sharing in select European cities reveals that the market is fast gaining ground. Residents in a number of cities in France, Germany as well as in the UK are currently multi-modal transport users. While only one out of four claim familiarity with the car sharing concept, once familiar, the interest levels in these services zip to 38 per cent.
  • Automating enforcement of environmental zones
    July 27, 2012
    Amsterdam City Council has chosen to move away from manual enforcement of its environmental zone, which is intended to keep highly polluting goods vehicles out of the city centre, and is installing an automated, ANPR-based system. The signs are not much to look at: white with a red circle and the all-important word Milieuzone ('Environmental zone'). But these signs mean that Amsterdam's city centre is strictly off-limits to polluting goods traffic. At the moment compliance is monitored by special wardens wh