Situated in San Diego County, California, the growing city of San Marcos has seen its population increase by 53.5 per cent since the turn of the century. Although this dramatic population increase has spurred economic growth bringing new business, homes and opportunities to the city, it has also increased traffic congestion along its central corridor, San Marcos Boulevard. This became the most congested arterial in the city, and, by 2006, the second-most travelled corridor in San Diego County.
January 20, 2012 Read time: 4 mins

Situated in San Diego County, California, the growing city of 798 San Marcos has seen its population increase by 53.5 per cent since the turn of the century. Although this dramatic population increase has spurred economic growth bringing new business, homes and opportunities to the city, it has also increased traffic congestion along its central corridor, San Marcos Boulevard. This became the most congested arterial in the city, and, by 2006, the second-most travelled corridor in San Diego County.

The corridor, though less than 6km long, accommodates as many as 46,000 motorists per day and is home to two schools and a multitude of businesses. The fourlane corridor has 17 major and minor intersections, including a couple of signals at freeway ramps.


The largest challenge for this corridor is three peak travel periods during the day; morning, midday and evening.

To help combat the growing traffic congestion, city traffic engineers were tasked with finding a way to improve traffic flow. The ideal solution would use ITS technologies, rather than expanding the existing four-lane roadway to the six lanes necessary to accommodate such large daily traffic volumes. From this, the 'Smart Corridor' project was born.

Project:

Reduce traffic congestion on busy arterial

Project Costs: US$671,000

Benefits:

• First-year savings: $645,000
• Lifetime savings: $5.1 million
• Delay time reduction: Up to 46 per cent
• Cost benefit ratio: 8:1

Vast improvement

"The idea behind the Smart Corridor project was to find a technology that would truly optimise the boulevard," says Omar Dayani, principal civil engineer for the City of San Marcos. "We needed to enhance traffic flow with a solution that would provide the maximum benefit to the public at a minimal cost to the city. A report by the 831 Federal Highway Administration (FHWA) showed that adaptive traffic signal control technology yielded, on average, a 10 per cent improvement in performance metrics including travel time, delay, stops, emissions and fuel consumption. 10 per cent sounded like a vast improvement to us, but we were striving for more.

After much research and consideration, my team and I chose to employ an adaptive control system, QuicTrac by 772 McCain, to maximise our results."

Deployment

The San Marcos Boulevard project was primarily funded by the Traffic Light Synchronization Program (TLSP) with a 15 per cent local match. The deployment went through two stages of optimisation.

First, the city used historical traffic flow data to better coordinate signal timing along the corridor. After the initial stage was successfully installed and working, the city's consulting firm laid the groundwork for phase two: adaptive control software. The adaptive software took the coordinated signal timing a step further by capturing and using realtime traffic conditions to optimise timing along the corridor. The system went through several rounds of testing and tweaks before it was fully operational.

"Every highly travelled arterial has its challenges different from the next, so it is imperative to choose a software partner that will work with your city's specific conditions," says Jason Stack, principal for Stack Traffic Consulting.

System results

Following the implementation of adaptive software, the city conducted a data analysis to determine the success of the project. Results showed significant improvements in delay times and corridor speed. The findings indicated that commuters driving the corridor experienced results as high as a 46 per cent and 39.1 per cent reduction in delay time and stops, respectively. Averaged over the three peak periods, and considering travel in both directions, the system yielded 19.5 per cent fewer stops, a 5.8 per cent speed increase, and a 7.1 per cent reduction in fuel consumption.

"Results for the adaptive software system met our expectations," states Omar. "The study indicated a 46 per cent reduction in delay time in the eastbound direction (the peak direction) during the evening peak period. That means less stop-and-go traffic yielding reduced travel times, emissions and probability of accidents. However, there was no significant improvement in westbound direction during this period." The City of San Marcos undertook a financial analysis which concluded total savings of $645,000 in the first year and $5.1 million over the lifetime of the project, with a benefit:cost ratio of 8:1. The calculations included cost benefits of travel time savings, fuel consumption savings, and reduced emissions of reactive organic gases, nitrogen oxides, particulate matter (PM10s), and carbon dioxide. An additional cost, not calculated in this report, is the health impact that congestion plays on city residents, recently quantified in The Public Health Costs of Traffic Congestion Study by Harvard University. The study shows that traffic congestion-related gas emissions caused approximately 3,000 premature deaths in 2005 with a total social cost of $24 billion in healthcare-related expenses. The bottom line is that by employing adaptive signal control software, the city of San Marcos effectively reduced traffic congestion, saving the community time, money, and healthcare-related expenses.

For more information on companies in this article

Related Content

  • Real time active traffic management improves travel times
    July 17, 2012
    Traffic management centres (TMC) have traditionally served to provide surveillance and responses to traffic incidents and recurring and non-recurring changes in road networks. Typically, a TMC collected field data from the roadway and transit infrastructure and provided the integration necessary for operators to see what was happening and then coordinate a response. Standard operating procedures (SOPs) guided operators on how to respond to a given situation. It eventually became impractical for TMC operat
  • Traffic signal priority initiatives aid better bus travel
    March 15, 2012
    David Crawford investigates traffic signal priority initiatives developing for better bus travel on the US Pacific Coast Transit patronage rises by an average of 35% along commuter corridors equipped with bus rapid transit (BRT) systems, according to the US Department of Transportation’s Federal Transit Administration (FTA). BRT as defined as bus transit enhanced with ITS systems for better services, is winning new passengers attracted by opportunity to avoid increasing fuel costs and traffic congestion.
  • Challenges and benefits of adaptive signal control
    April 23, 2013
    Delcan’s Joe Lam, who managed the first computerised signal system in the world, provides an expert insight into adaptive signal control. There are no gadgets in the world that regulate our daily behaviour as much as traffic signals, except perhaps our mobile phones. It has been estimated that the daily commuter goes through at least 10 signals on his journey to work. However, unlike mobile phones, traffic signals cannot be ignored or switched off by their daily users, at least not without legal consequence