FTA disappointed at Dartford free-flow toll delay

‘The delay of the introduction of free-flow tolls at Dartford River Crossing disappointing as it may present additional costs to industry’ is the message from the Freight Transport Association (FTA). The Association has voiced its concern in response to the announcement by the Highways Agency (HA) that the planned technology to allow motorists to use the crossing without having to stop at barriers and pay is to be delayed by up to four weeks. Originally planned to be in place by the 28 October 2014, th
September 22, 2014 Read time: 4 mins
‘The delay of the introduction of free-flow tolls at Dartford River Crossing disappointing as it may present additional costs to industry’ is the message from the 6983 Freight Transport Association (FTA).  The Association has voiced its concern in response to the announcement by the 503 Highways Agency (HA) that the planned technology to allow motorists to use the crossing without having to stop at barriers and pay is to be delayed by up to four weeks.
 
Originally planned to be in place by the 28 October 2014, the HA has now said that the system will now not be ready to use until late November.
 
Malcolm Bingham, FTA’s head of Road Network Management Policy said: “This is disappointing news that the free-flow tolling at Dartford is now to be delayed – the costs of this hold-up are unacceptable to the freight industry. FTA has been asking for a long time for this system to be introduced as this is the appropriate way forward in order to reduce a good deal of administration costs for the freight industry in dealing with tolls, charges and queues at the crossing.”
 
FTA has previously expressed support of the free-flow system, saying that ‘it would be good news for the freight industry’ within its response to the 1837 Department for Transport consultation on the proposals to revise the road charging regime.  On behalf of its members, the Association stated that freight operators have always maintained that the toll plazas themselves cause the majority of the congestion at the crossing.  According to FTA figures, at present it already costs an estimated £1 per minute per HGV in running costs to queue at the Dartford tolls.
 
The free-flow technology will allow motorists to use the crossing without having to stop at barriers to hand over payment, and instead they will be able to pay through a variety of methods including telephone, text message, online and at retail outlets, giving drivers greater flexibility in how and when they pay the charge.
 
Bingham added: “However, we need to be sure that the system will work, and it is therefore vital that they get it right.   FTA has and will continue to work with the Highways Agency to help get a resolution to this issue as soon as possible.”

According to the HA, the full benefits of the scheme will be delivered by the end of April 2015, when all changes to the road layout will be completed. The website, systems and infrastructure needed to operate these new arrangements have been installed and are currently being tested to ensure that they operate reliably and are easy to use.

The timetable will ensure that drivers have enough notice to prepare for the changes and that the system is fully tested before it is introduced.

Highways Agency project leader Nigel Gray said: “Dart Charge is a massive change for drivers using the Dartford Crossing and it’s only right that it is thoroughly tested before being introduced.

“We want to help drivers to be ready for the improvements we’re making at the Crossing. That’s why we are saying today that Dart Charge will start during late November.  We can reassure drivers that we’ll give them plenty of notice before the changes are introduced. They will have considerable time to sign up for a pre-pay account, which for most will be the easiest and cheapest way to pay the charge – with discounts of up to a third on every crossing.”

Until Dart Charge goes live, the current payment arrangements for the road user charge at the Crossing will continue - cash at the Crossing, through a DART-Tag or local residents account.

For more information on companies in this article

Related Content

  • Pilot scheme tests automatic emergency call system
    March 14, 2012
    Development of the European eCall system is now at a stage of national systems testing. Ertico’s project manager for the HeERO pilot scheme Andy Rooke has given ITS International the lowdown on progress towards pan-European eCall services. Live testing is now under way in the nine countries participating in the European Commission’s HeERO project – a three year pilot scheme preparing the way for full deployment of Europe’s eCall automatic emergency call system.
  • Russia 2018 World Cup: ITS can win it
    June 5, 2018
    Teams and supporters will cover vast distances in Russia for the 2018 FIFA World Cup. Stephane Clauss from Sony Europe’s Image Sensing Solutions division examines how the latest camera technologies can be deployed to help things run smoothly over the next month or so... For one month, from June 14, Russia is hosting the 2018 FIFA World Cup. This is the largest country in the world and the distances between venues will be larger than at almost any other World Cup - bar the finals in the US and Brazil.
  • New approach to real time travel information - free of charge
    February 3, 2012
    Austria's national road operator, ASFINAG, has launched the TMCplus traveller information service which is unusual in that it offers encrypted-level services to all users free of charge. Martin Müllner writes
  • Major upgrade for Mississippi bridges
    September 3, 2013
    Four major bridges over the lower Mississippi are to get intelligent transportation systems (ITS) upgrades, thanks to a US$10 million grant from the US Department of Transportation TIGER (Transportation Investment Generating Economic Recovery) fund. The project will expand existing ITS systems in each of the three states to complement previous state and private investments.