Bi-State board votes to restart tolling services procurement

The Kentucky-Indiana Joint Board for the Ohio River Bridges Project has voted to restart the procurement of a tolling services provider. The vote comes after the Indiana Finance Authority’s review of a protest submitted by a non-winning bidder in late September. The Joint Board heard from the IFA that the allegations made in the protest were unsubstantiated, but the agency did uncover a significant potential personal and organisational conflict of interest regarding financial arrangements between a subc
October 28, 2014 Read time: 3 mins
The Kentucky-Indiana Joint Board for the Ohio River Bridges Project has voted to restart the procurement of a tolling services provider. The vote comes after the Indiana Finance Authority’s review of a protest submitted by a non-winning bidder in late September.

The Joint Board heard from the IFA that the allegations made in the protest were unsubstantiated, but the agency did uncover a significant potential personal and organisational conflict of interest regarding financial arrangements between a subcontractor of the preferred proposer and a subcontractor of the Joint Board’s toll advisor. The conflict of interest and the appearance of impropriety it creates were substantial enough that the joint board voted to terminate and restart the procurement.

“The best ethical and objective path forward is to cancel the existing procurement and reset the process,” said Kendra York, director of the IFA. “While there was no evidence that the conflict of interest actually influenced the procurement decision, we owe it to the people of Indiana and Kentucky to safeguard their confidence in the process.”

York said prior proposing parties will be allowed to participate in the restart process “without disqualification or prejudice” as a result of the procurement cancellation.

“We have been committed to transparency throughout this project, and that includes our procurement processes,” said Kentucky Transportation Secretary Mike Hancock. “The issue at hand is a conflict of interest, which has now been removed. The restart of the toll system provider procurement can now begin, and we will keep the project on schedule.”

The potential conflict of interest existed between ClearStrategyConsulting, subcontractor to Computer Aid (CAI), the tolling advisor hired by the Joint Board, and Gude Management Group, a subcontractor on the 4984 Kapsch TrafficCom proposal.

The Joint Board will remove CAI as its toll advisor and appoint Parsons Transportation Group as the new interim toll advisor. CAI will serve out an amended contract, which is limited to transitioning the advising role to 4089 Parsons and completing certain tasks unrelated to the procurement. The 6198 Kentucky Transportation Cabinet will establish a new procurement to secure a new, long-term toll advisor.

The IFA requires full disclosure of known conflicts of interest. Board officials do not believe that Kapsch knew of the conflict of interest between its subcontractor and CAI’s subcontractor.

Board officials also believe the restart will not affect the anticipated start date for tolling.

Related Content

  • March 13, 2015
    Kapsch preferred bidder on Ohio River Bridges toll project
    The Indiana Finance Authority (IFA) and Ohio River Bridges Joint Board have again selected Kapsch TraffiCom to manage and maintain an all-electronic toll-collection system for the Louisville-Southern Indiana Ohio River Bridges Project. Kapsch TrafficCom was selected from among three bidders who participated in the proposal process. A joint evaluation committee, made up of officials from both Indiana and Kentucky, scored the proposals based on the best value. Kapsch TrafficCom's proposal estimate was US$41.5
  • September 16, 2014
    Kapsch preliminary preferred vendor for Ohio bridge toll project
    The Kentucky-Indiana Joint Board has unanimously selected Kapsch TrafficCom as the preliminary preferred proposer in the competition to provide an electronic toll system for the bi-state Ohio River Bridges project. The board’s action followed independent staff reviews of technical and financial proposals submitted by the competing firms. Kapsch was one of six interested companies that the board in January deemed qualified to submit proposals for the toll system provider (TSP) contract. The Indiana Fin
  • December 21, 2016
    Ohio River Bridges East End crossing project opened to traffic
    The Ohio River Bridges East End Crossing, now named the Lewis and Clark Bridge, has opened to traffic to connect SR 265 in Indiana with the Gene Snyder Freeway in Kentucky, marking the substantial completion of the $2.3 billion Louisville Southern Indiana Ohio River Bridges project, which included the Downtown Crossing, now named the Abraham Lincoln Bridge. Parsons was the lead partner in the Community Transportation Solutions joint venture (JV). The JV served as the overall project’s general engineerin
  • May 14, 2015
    Kapsch TrafficCom to provide toll system the Louisville-Southern Indiana Ohio River Bridges
    Kapsch TrafficCom North America has been awarded a US$41 million contract by the Indiana Finance Authority (IFA) to provide the toll system for the Louisville-Southern Indiana Ohio River Bridges (LSIORB). The comprehensive project includes the installation, integration, operation, and maintenance of an end-to-end open road toll collection system, as well as back office system and customer service centre operation at the three bridges that will connect Louisville, Kentucky and Jeffersonville, Indiana. As