Strabag consortium to build section of S5 expressway in Poland

A consortium consisting of Strabag subsidiary Heilit+Woerner and Budimex is to build a 48 kilometre section of the S5 expressway between Poznań and Wrocław in Poland. Work on the US$185 million project is due to begin in around four weeks and is expected to last 30 months. Completion and commissioning of the new section are scheduled for 2017.
August 6, 2014 Read time: 2 mins

A consortium consisting of 3861 Strabag subsidiary Heilit+Woerner and Budimex is to build a 48 kilometre section of the S5 expressway between Poznań and Wrocław in Poland.  

Work on the US$185 million project is due to begin in around four weeks and is expected to last 30 months. Completion and commissioning of the new section are scheduled for 2017.

The entire new section of the S5 north of Wrocław from Korzeńsko to Widawa measures approx. 48 km in length. The contract includes the planning and construction of the first 15 kilometre long section and includes the construction of two interchanges as well as access roads. The road consists of two lanes of traffic in each direction, with the width of the median strip designed to allow the future expansion of the traffic volume through the addition of a third lane.

Under the project, the consortium will build 14 bridge structures, technical infrastructure facilities such as rain channels, gas lines and illumination, as well as road passages and two rest stations. At the same time, it will also be necessary to upgrade the existing drainage network and ditches. The greenery will be partially removed, adapted or protected and re-planned at the end of the construction phase.

For more information on companies in this article

Related Content

  • Chile awards China $1.1bn toll deal
    April 12, 2021
    CRCC will have concession on 195km Talca-Chillán toll highway on Route 5
  • Consortium awarded LRT project in Canada
    February 12, 2016
    TransEd Partners, a consortium including global engineering and construction company Bechtel, has been selected by the City of Edmonton to finance, design, supply vehicles, build, operate, and maintain the first phase of the Edmonton Valley Line Light Rail Transit project. The Valley Line is central to the City of Edmonton's transportation plan, designed to meet the demands of Canada's second fastest-growing city that is expected to increase in size by 50 per cent by 2040.
  • Temporary CCTV poses more challenges than permanent installations
    June 12, 2015
    Long-term roadworks pose particular problems for temporary surveillance installations. Converting the hard shoulder to a running lane, either full- or part-time, is the UK Highways Agency’s solution to ease motorway congestion. This is leading to a number of long-term projects where large stretches of the hard shoulder are closed off by temporary concrete barriers and during these roadwork programmes, temporary CCTV cameras are deployed to monitor and record vehicle traffic and workers.
  • High-res traffic data provides planners with the big picture
    November 5, 2015
    Road authorities have a lot to gain from high-resolution traffic data, argues Pravin Varaiya. Traffic engineers have traditionally been forced to operate with limited data regarding the performance of their arterials. Traffic studies are often commissioned once every three years, over a few days, to get an updated estimate of utilization.