Strabag consortium awarded HS2 high speed rail civil engineering contract

The SCS consortium, comprising Strabag, Skanska and Costain has been awarded the main work civil contract packages for lots S1 and S2 of the UK’s new HS2 high-speed railway that will initially link London to Birmingham and later to Leeds and Manchester. The contract is divided into two stages. Stage 1 requires the contractor to design, plan and estimate the works within a period of 16 months, which will serve as the basis for determining the target price for stage 2, the actual construction phase.
August 1, 2017 Read time: 1 min
The SCS consortium, comprising 3861 Strabag, 7136 Skanska and 2002 Costain has been awarded the main work civil contract packages for lots S1 and S2 of the UK’s new HS2 high-speed railway that will initially link London to Birmingham and later to Leeds and Manchester.


The contract is divided into two stages. Stage 1 requires the contractor to design, plan and estimate the works within a period of 16 months, which will serve as the basis for determining the target price for stage 2, the actual construction phase.

The design phase is to be completed in 2018. Construction is scheduled to last until 2023 with the first trains running in 2026.

Related Content

  • August 11, 2021
    Consortium to study UK eHighway feasibility 
    Partners including Siemens hope overhead electricity lines will serve major roads by 2030s
  • September 14, 2021
    Norway gets ready for more EVs
    Norway’s road transport network is changing radically. The country is gearing up for greater electric vehicle use as well as gradually phasing out its traditional ferry links
  • July 28, 2015
    Hitachi Rail Europe wins UK first traffic management contract
    Passengers on some of the busiest commuter lines in the UK can look forward to more frequent and more reliable trains following a deal to provide new traffic management technology on the Thameslink route through central London. Network Rail and the Thameslink Programme have signed a contract with Hitachi Rail Europe (HRE) to deliver a step-change in technology through state-of-the-art traffic management technology.
  • December 1, 2016
    Finnish light rail contract awarded
    Finnish organisations Pöyry, YIT and VR Track are to implement the Tampere light rail project on behalf of the City of Tampere for the implementation of the Tampere light rail project. The revised cost estimate for the implementation stage is US$2154.5 million (€238.8 million). The first phase of construction will commence in the first half of 2017 and is expected be complete by 2021. During this phase, the new rail line will be extended by 15 kilometres and a depot will be constructed in Hervanta. The