Skip to main content

São Paulo court stalls undersea tunnel

São Paulo state court TCE-SP has ordered a halt to the tender of São Paulo state's US$732 million project to build an underwater tunnel between the coastal cities of Santos and Guarujá. The project calls for the construction and operation of a 900 metre, six-lane submersed tunnel between Brazil's coastal cities of Santos and Guarujá. To be submerged at a depth of 21 metres, the tunnel would give the Santos port navigation channel a draft of 17 metres. Construction was scheduled to start in 2014 and c
February 3, 2015 Read time: 2 mins
São Paulo state court TCE-SP has ordered a halt to the tender of São Paulo state's US$732 million project to build an underwater tunnel between the coastal cities of Santos and Guarujá.

The project calls for the construction and operation of a 900 metre, six-lane submersed tunnel between Brazil's coastal cities of Santos and Guarujá. To be submerged at a depth of 21 metres, the tunnel would give the Santos port navigation channel a draft of 17 metres.

Construction was scheduled to start in 2014 and completed by2017.

The move responded to claims by bidding companies that there were a number of inconsistencies in the tender rules and that the time provided by state highway company

5947 Dersa, in charge of the tender process, was insufficient for proposals to be drawn up, according to local reports. Dersa now has five days to respond to the uncertainties and submit a copy of the bidding rules for TCE-SP analysis.

The tunnel is expected to take 44 months to build once the contract is awarded, São Paulo governor Geraldo Alckmin has said.

For more information on companies in this article

Related Content

  • Asecap debates the future of tolling
    August 23, 2016
    Colin Sowman reports form Asecap’s Study & Information Days event in Madrid. At Asecap’s (the Association of European Toll Road Operators) recent Study and Information Days event there was no doubt about the subject at the top of the agenda: the European Union Directive 23/2014/EU. This will introduce fundamental changes to the concession model under which Asecap members operate more than 50,000km of tolled highways and, in response, it has compiled a report entitled Proposal for a Sustainable Concession Mo
  • Moxa provides clear vision for Caldecott Tunnel’s Fourth Bore
    September 15, 2014
    Caldecott Tunnel’s new Fourth Bore is utilising a bespoke high-capacity monitoring and communications network from Moxa. The Caldecott Tunnel connects Contra Costa and Alameda counties in Northern California and traditionally it has suffered severe congestion - especially during peak hours. Opened in 1937 as a twin-bore arrangement, by 1964 the increase in traffic volumes led to a third bore being added. Shortly after the third bore was opened a tidal flow was introduced with the centre bore alternating in
  • Growth of legislation in favour of US enforcement market
    February 1, 2012
    The automated road safety enforcement industry in the United States had a very robust 2010. The industry continued to grow to the point that providers now have nearly 5,000 cameras deployed in 25 of the 50 states and the District of Columbia, with more than 650 communities utilising such life-saving technology. Intersection safety cameras are the most common application but more communities are also implementing road safety camera programmes to deter excessive speeding. Deploying cameras to protect children
  • Mexico developing highway projects
    August 29, 2014
    Mexico's transport and communications ministry, SCT, is developing 46 highway projects, worth US$12.3 billion, to be completed by 2018. "We have 28 highways under construction, eight were recently finished, and construction on an additional seven highways will start before the end of the year, said SCT minister Gerardo Ruiz, during the launch of construction of the Cardel-Poza Rica highway. A consortium led by Mota-Engil won a 30-year concession for the 129 kilometre Cardel-Poza Rica highway concessi