Skip to main content

São Paulo court stalls undersea tunnel

São Paulo state court TCE-SP has ordered a halt to the tender of São Paulo state's US$732 million project to build an underwater tunnel between the coastal cities of Santos and Guarujá. The project calls for the construction and operation of a 900 metre, six-lane submersed tunnel between Brazil's coastal cities of Santos and Guarujá. To be submerged at a depth of 21 metres, the tunnel would give the Santos port navigation channel a draft of 17 metres. Construction was scheduled to start in 2014 and c
February 3, 2015 Read time: 2 mins
São Paulo state court TCE-SP has ordered a halt to the tender of São Paulo state's US$732 million project to build an underwater tunnel between the coastal cities of Santos and Guarujá.

The project calls for the construction and operation of a 900 metre, six-lane submersed tunnel between Brazil's coastal cities of Santos and Guarujá. To be submerged at a depth of 21 metres, the tunnel would give the Santos port navigation channel a draft of 17 metres.

Construction was scheduled to start in 2014 and completed by2017.

The move responded to claims by bidding companies that there were a number of inconsistencies in the tender rules and that the time provided by state highway company

5947 Dersa, in charge of the tender process, was insufficient for proposals to be drawn up, according to local reports. Dersa now has five days to respond to the uncertainties and submit a copy of the bidding rules for TCE-SP analysis.

The tunnel is expected to take 44 months to build once the contract is awarded, São Paulo governor Geraldo Alckmin has said.

Related Content

  • Asking drivers what information they need: radical but effective
    March 19, 2014
    When Texas A&M Transportation Institute was asked to devise a temporary traveller information system for work zones, it started by asking drivers what they need. Robert Brydia explains the thinking, implementation and results. US Interstate 35 (I-35) runs roughly north–south originating in Laredo, Texas and ends 1,500 miles away in Duluth, Minnesota having passed through Oklahoma, Kansas, Missouri and Iowa. Within Texas the I-35 splits into I-35E and I-35W passing through Dallas and Fort Worth respectiv
  • Kenya plans road toll tenders
    March 25, 2015
    Kenya plans to start tendering in May for toll-road contracts estimated by the government to be worth $2 billion to improve the efficiency of the East African nation’s biggest commercial routes, according to Bloomberg. The contracts will be in addition to the 45 deals worth about US$3.2 billion that the government will start awarding as early as next week, to double the nation’s paved-road network through an annuity program. The government is planning to introduce five toll projects covering about 800 kilom
  • Traffic to flow freely over world’s widest bridge
    November 13, 2012
    Pete Goldin reports on a new Egis project in Canada, providing open road tolling operations for the widest bridge in the world. A bridge can present a bottleneck in a system of roads or it can support the smooth and unobstructed flow of traffic. Much depends on the bridge design, surrounding infrastructure and tolling system. By adding lanes and deploying open road tolling (ORT), the new Port Mann Bridge located in the metropolitan Vancouver area in British Columbia, will alleviate congestion at one of the
  • Norway gets ready for more EVs
    September 14, 2021
    Norway’s road transport network is changing radically. The country is gearing up for greater electric vehicle use as well as gradually phasing out its traditional ferry links