Rail industry, regulators debate feasibility of PTC

US rail industry officials and federal accident regulators have disagreed about the viability of a looming mandate that most US railways be equipped with automated control systems by the end of next year. Congress is requiring that most major railroad companies install automated systems known as positive train control (PTC) by December 2015. Automated train systems have gained renewed attention after a spate of high-profile accidents on passenger and freight railways, including most recently a Decem
March 10, 2014 Read time: 3 mins

US rail industry officials and federal accident regulators have disagreed about the viability of a looming mandate that most US railways be equipped with automated control systems by the end of next year.

Congress is requiring that most major railroad companies install automated systems known as positive train control (PTC) by December 2015.

Automated train systems have gained renewed attention after a spate of high-profile accidents on passenger and freight railways, including most recently a December derailment of a freight train in North Dakota that resulted in 400,000 gallons of crude oil being spilled.

The law requiring the implementation of automated train control systems by 2015 has been on the books since 2008.

However, Association of American Railroads President Ed Hemberger told members of the Senate Commerce, Science and Transportation Committee that the automated systems have proven to be more difficult to install than regulators imagined.

"PTC is an unprecedented challenge, both in terms of the technologies to be used and the integration of those technologies," Hemberger told the panel in testimony submitted before Thursday's hearing.

"The railroad industry began working several years ago with the 2115 Federal Communications Commission (FCC) to licence the wireless spectrum necessary for PTC,” he said.  However, under the FCC’s interpretation of Section 106 of the National Historic Preservation Act (NHPA), railroads must ascertain, on an antenna-by-antenna basis, if the antennas will negatively impact areas of historic, cultural, or religious significance.

Hemberger said the railroads were in agreement with federal regulators about the importance of installing automated train control systems to boost safety.  But the rail association chief said the only solution to the challenges facing the train industry was to push back the 2015 deadline for them to automate.

"The bottom line is that without further changes to the FCC approval process, the timeline for ultimate deployment of PTC will be delayed significantly," Hemberger said.

5628 National Transportation Safety Board (NTSB) Vice Chairman Chris Hart said the safety benefits of automating trains should outweigh the rail industry's technical concerns.

"Implementation of PTC systems was included on the NTSB’s Most Wanted List when the list was First published in 1990 and has remained on the list almost continuously since that time," Hart said. "We may never eliminate human error from the railroad system, but PTC provides a level of redundancy to protect trains and those on board when human factors, such as distraction or fatigue, might otherwise set an accident sequence into motion." 

Related Content

  • July 24, 2013
    San Diego rail line gets positive train control
    Rail Technology supplier Wabtec is to supply Herzog Technologies to provide with positive train control (PTC) equipment and services for Oceanside, California’s North County Transit District (NCTD) in a deal worth US$9 million. The contract includes an option worth an additional US$5 million. Under the initial contract, Wabtec will provide its interoperable electronic train management system (I-ETMS) equipment and installation for seven locomotives and ten passenger transit cab cars on NCTD's Coaster train,
  • June 23, 2014
    ITS America, automakers respond to Rubio-Booker 5.9 GHz spectrum legislation
    The Intelligent Transportation Society of America (ITS America) and US automakers have responded to the announcement on legislation introduced by US Senators Marco Rubio and Cory Booker that would set deadlines on the Federal Communications Commission (FCC) for developing and publishing a test plan for the use of unlicensed devices in the 5.9 GHz band. The senators introduced S. 2505, the Wi-Fi Innovation Act, legislation to expand unlicensed spectrum use by requiring the Federal Communications Commissio
  • February 1, 2012
    Legalities of in-vehicle systems and cooperative infrastructures
    Paul Laurenza of Dykema Gossett PLLC discusses the paths which lawmakers may go down on the route to making in-vehicle systems and cooperative infrastructures a reality. The question of whether or not to mandate in-vehicle systems for safety and other applications is a vexed one. There is a presumption on some parts that going down the road of forcing systems' fitment is somehow too domineering or restricting. Others would argue that it is the only realistic way of ensuring that systems achieve widespread d
  • January 21, 2025
    C-V2X: the final countdown
    It’s finally here: the Federal Communications Commission has cleared the way to mass deployment of C-V2X in a bid to put a much-needed brake on the US’s road crash stats