Major setback for California's high speed train

The future of the California high speed rail project hangs in the balance as a result of two rulings handed down by Sacramento Superior Court Judge Michael Kenny on 25 November. "The judge's ruling will prevent the [California High-Speed Rail] Authority from spending bond measure funds for construction until the funding plan is brought into compliance," said Michael Brady, co- lead attorney on the case, but because that would require finding at least US$25 billion in extra funds, Brady believes complianc
November 28, 2013 Read time: 2 mins
The future of the California high speed rail project hangs in the balance as a result of two rulings handed down by Sacramento Superior Court Judge Michael Kenny on 25 November.

"The judge's ruling will prevent the [California High-Speed Rail] Authority from spending bond measure funds for construction until the funding plan is brought into compliance," said Michael Brady, co- lead attorney on the case, but because that would require finding at least US$25 billion in extra funds, Brady believes compliance seems "virtually impossible." They need to step back and rethink their whole approach," added co-lead attorney Stuart Flashman.

The Authority’s Chairman, Dan Richard, tried to cast the court decision in a more positive light. "The judge did not invalidate the bonds as approved by the voters," he said. "Like all transformative projects, we understand that there will be many challenges that will be addressed as we go forward in building the nation’s first high-speed rail system."

The court rulings are the culmination of prolonged litigation that began two years ago when Kings County Board of Supervisors filed a lawsuit asserting that the Authority failed to comply with certain statutory requirements in its 2011 funding plan.

In his 25 November opinion, Judge Kenny did not explicitly address this potential funding deficiency nor did he agree to rescind existing contracts with Tutor-Perini and 3879 Caltrans or rule on the propriety of using federal grant money, as requested by the plaintiffs.

Instead, he ruled that the Authority cannot "proceed to commit and spend Proposition 1A bond proceeds for construction or property acquisition" until it has complied with the requirements stated in his 16 August ruling, when he ruled that the Authority failed to comply with the requirements of Proposition 1A in two fundamental respects:  It was unable to certify completion of all the environmental clearances for the 300-mile Initial operating segment (IOS) extending from Merced to San Fernando Valley; and it was unable to identify "reasonably expected" sources of funds required to complete the Initial operating segment.

Related Content

  • September 20, 2012
    Developing integrated transport networks
    A major initiative in managing numerous transport networks as a single system has moved into a significant phase with design of sophisticated new ITS systems. Jon Masters reports. Detailed design work is under way on two pilot projects pursuing a common principle – that transportation can be made more efficient or effective if the various networks and modes of travel are managed as a whole system. This is the central tenet of the US Department of Transportation’s (USDOT) Integrated Corridor Management (ICM)
  • July 29, 2013
    Asian high speed rail link tender expected late 2014
    Officially launched in February 2013, tenders for the high-speed rail link project between Kuala Lumpur and Singapore will be received towards the end of 2014, Mohd Nur Kamal, the CEO of Malaysia's Land Public Transport Commission (SPAD) has announced. Although the two governments continue to work on technical details and feasibility studies, various parties have already voiced an interest. The railway, which will connect the two countries at speeds exceeding 300 km/h, will reduce the journey time between t
  • June 5, 2018
    MaaS must be seamless and invisible - or forget it
    MaaS experts from around the world converged on ITS International’s MaaS Market Atlanta conference to talk about how MaaS can be implemented in the US. Andrew Bardin Williams had a front row seat. Transportation experts from around the world gathered in the US earlier this month to discuss the future of Mobility as a Service (MaaS) and how it could be deployed in the US market. While most attendees at ITS International’s MaaS Market Atlanta conference were familiar with the MaaS concept, the US’s highly
  • September 29, 2015
    Vendor workshop for California Road Charge Pilot Project
    In December 2015 the California Road Charge Technical Advisory Committee (TAC) will complete its pilot project design recommendations as directed by California Senate Bill 1077 (2014). Vendor procurement will begin once the TAC’s recommendations are complete and submitted. The pilot test is scheduled to commence in summer 2016. D’Artagnan Consulting is hosting a workshop on 4-6 November on behalf of the California State Transportation Agency and the California Department of Transportation for vendors int