The future of the California high speed rail project hangs in the balance as a result of two rulings handed down by Sacramento Superior Court Judge Michael Kenny on 25 November. "The judge's ruling will prevent the [California High-Speed Rail] Authority from spending bond measure funds for construction until the funding plan is brought into compliance," said Michael Brady, co- lead attorney on the case, but because that would require finding at least US$25 billion in extra funds, Brady believes complianc
November 28, 2013 Read time: 2 mins
The future of the California high speed rail project hangs in the balance as a result of two rulings handed down by Sacramento Superior Court Judge Michael Kenny on 25 November.

"The judge's ruling will prevent the [California High-Speed Rail] Authority from spending bond measure funds for construction until the funding plan is brought into compliance," said Michael Brady, co- lead attorney on the case, but because that would require finding at least US$25 billion in extra funds, Brady believes compliance seems "virtually impossible." They need to step back and rethink their whole approach," added co-lead attorney Stuart Flashman.

The Authority’s Chairman, Dan Richard, tried to cast the court decision in a more positive light. "The judge did not invalidate the bonds as approved by the voters," he said. "Like all transformative projects, we understand that there will be many challenges that will be addressed as we go forward in building the nation’s first high-speed rail system."

The court rulings are the culmination of prolonged litigation that began two years ago when Kings County Board of Supervisors filed a lawsuit asserting that the Authority failed to comply with certain statutory requirements in its 2011 funding plan.

In his 25 November opinion, Judge Kenny did not explicitly address this potential funding deficiency nor did he agree to rescind existing contracts with Tutor-Perini and 3879 Caltrans or rule on the propriety of using federal grant money, as requested by the plaintiffs.

Instead, he ruled that the Authority cannot "proceed to commit and spend Proposition 1A bond proceeds for construction or property acquisition" until it has complied with the requirements stated in his 16 August ruling, when he ruled that the Authority failed to comply with the requirements of Proposition 1A in two fundamental respects:  It was unable to certify completion of all the environmental clearances for the 300-mile Initial operating segment (IOS) extending from Merced to San Fernando Valley; and it was unable to identify "reasonably expected" sources of funds required to complete the Initial operating segment.

Related Content

  • November 11, 2016
    ARTBA: voters want transportation investment
    The preliminary US election results showed that voters in 22 states approved ballot measures that will provide US$201 billion in funding extensions and new revenue for state and local transportation projects, according to the American Road & Transportation Builders Association’s Transportation (ARTBA).
  • October 25, 2013
    US taps into European high-speed rail knowledge
    Representatives of major US high-speed rail projects are to meet with their European counterparts to seek the expertise and knowledge of the leading European high-speed rail companies. The US is planning to invest approximately US$150,000 million over the next ten years in the development of high-speed rail networks, representing a great opportunity for European infrastructure and engineering companies. For the first time, American senior official representatives of these projects will meet in Europe loo
  • January 23, 2012
    Changing driving conditions need ongoing driver training
    Trevor Ellis, chairman of the ITS UK Enforcement Interest Group, considers the role of ongoing driver training in increasing compliance. It is over 30 years since I passed my driving test. The world was quite a different place then, in that there were only half the vehicles there are now on the UK's roads, mobile phones did not really exist and (in the UK at least) the vast majority of us drove cars which by today's standards exhibited dreadful dynamic stability and were woefully underpowered.
  • February 2, 2012
    Changes needed to Italy's enforcement tendering?
    Fixed penalty notices KRIA's co-founder and President Stefano Arrighetti discusses the events which led up to investigations into the fraudulent use of his company's T-RED red light enforcement system and his house arrest. Looking forward, he says, there needs to be fundamental reform of how Italy goes about the enforcement contract tendering process