Major setback for California's high speed train

The future of the California high speed rail project hangs in the balance as a result of two rulings handed down by Sacramento Superior Court Judge Michael Kenny on 25 November. "The judge's ruling will prevent the [California High-Speed Rail] Authority from spending bond measure funds for construction until the funding plan is brought into compliance," said Michael Brady, co- lead attorney on the case, but because that would require finding at least US$25 billion in extra funds, Brady believes complianc
November 28, 2013 Read time: 2 mins
The future of the California high speed rail project hangs in the balance as a result of two rulings handed down by Sacramento Superior Court Judge Michael Kenny on 25 November.

"The judge's ruling will prevent the [California High-Speed Rail] Authority from spending bond measure funds for construction until the funding plan is brought into compliance," said Michael Brady, co- lead attorney on the case, but because that would require finding at least US$25 billion in extra funds, Brady believes compliance seems "virtually impossible." They need to step back and rethink their whole approach," added co-lead attorney Stuart Flashman.

The Authority’s Chairman, Dan Richard, tried to cast the court decision in a more positive light. "The judge did not invalidate the bonds as approved by the voters," he said. "Like all transformative projects, we understand that there will be many challenges that will be addressed as we go forward in building the nation’s first high-speed rail system."

The court rulings are the culmination of prolonged litigation that began two years ago when Kings County Board of Supervisors filed a lawsuit asserting that the Authority failed to comply with certain statutory requirements in its 2011 funding plan.

In his 25 November opinion, Judge Kenny did not explicitly address this potential funding deficiency nor did he agree to rescind existing contracts with Tutor-Perini and 3879 Caltrans or rule on the propriety of using federal grant money, as requested by the plaintiffs.

Instead, he ruled that the Authority cannot "proceed to commit and spend Proposition 1A bond proceeds for construction or property acquisition" until it has complied with the requirements stated in his 16 August ruling, when he ruled that the Authority failed to comply with the requirements of Proposition 1A in two fundamental respects:  It was unable to certify completion of all the environmental clearances for the 300-mile Initial operating segment (IOS) extending from Merced to San Fernando Valley; and it was unable to identify "reasonably expected" sources of funds required to complete the Initial operating segment.

Related Content

  • December 18, 2018
    California to require all bus fleets to be zero-emission by 2040
    The California Air Resources Board (CARB) has approved a statewide regulation which will require public transit agencies to gradually transition to fully zero emission buses by 2040. The Clean Transit regulation is expected to help transit agencies reduce greenhouse gas emissions by 19 million metric tonnes, nitrogen oxides by 7,000 tonnes and particulate matter by 40 tonnes from 2020 to 2050. CARB says the regulation will improve air quality, especially in low-income communities. It could also help
  • September 25, 2014
    Dubai plans major transportation projects
    According to Mattar Al Tayer, chairman and executive director of Dubai’s Roads and Transport Authority (RTA), the authority is planning at least another 35 mega projects in the future after spending about US$19.8 billion so far in upgrading services in the city. Speaking at InnoTrans 2014 in Berlin, Al Tayer said work was progressing on projects related to Expo 2020. He said these would include the extension of the Red Line of the Dubai Metro, upgrading roads and junctions surrounding and leading to t
  • August 17, 2016
    Ford targets fully autonomous vehicle in 2021
    Ford has announced its intention to have a high-volume, fully autonomous vehicle in commercial operation in 2021. The new vehicle will be a Society of Automotive Engineers-rated level 4-capable vehicle without a steering wheel or gas and brake pedals. It is being specifically designed for commercial mobility services, such as ride sharing and ride hailing, and will be available in high volumes. SAE level 4 is one level below full automation and is defined as ‘mode-specific performance by an automated
  • July 20, 2012
    Debating a cost-effective means of road user charging
    Does GPS/GNSS-based technology provide a cost-effective means of charging or tolling on a national or international level, or are the issues pertaining to effective enforcement an obstacle. Here, leading equipment manufacturers debate the issue.