The future of the California high speed rail project hangs in the balance as a result of two rulings handed down by Sacramento Superior Court Judge Michael Kenny on 25 November. "The judge's ruling will prevent the [California High-Speed Rail] Authority from spending bond measure funds for construction until the funding plan is brought into compliance," said Michael Brady, co- lead attorney on the case, but because that would require finding at least US$25 billion in extra funds, Brady believes complianc
November 28, 2013 Read time: 2 mins
The future of the California high speed rail project hangs in the balance as a result of two rulings handed down by Sacramento Superior Court Judge Michael Kenny on 25 November.

"The judge's ruling will prevent the [California High-Speed Rail] Authority from spending bond measure funds for construction until the funding plan is brought into compliance," said Michael Brady, co- lead attorney on the case, but because that would require finding at least US$25 billion in extra funds, Brady believes compliance seems "virtually impossible." They need to step back and rethink their whole approach," added co-lead attorney Stuart Flashman.

The Authority’s Chairman, Dan Richard, tried to cast the court decision in a more positive light. "The judge did not invalidate the bonds as approved by the voters," he said. "Like all transformative projects, we understand that there will be many challenges that will be addressed as we go forward in building the nation’s first high-speed rail system."

The court rulings are the culmination of prolonged litigation that began two years ago when Kings County Board of Supervisors filed a lawsuit asserting that the Authority failed to comply with certain statutory requirements in its 2011 funding plan.

In his 25 November opinion, Judge Kenny did not explicitly address this potential funding deficiency nor did he agree to rescind existing contracts with Tutor-Perini and 3879 Caltrans or rule on the propriety of using federal grant money, as requested by the plaintiffs.

Instead, he ruled that the Authority cannot "proceed to commit and spend Proposition 1A bond proceeds for construction or property acquisition" until it has complied with the requirements stated in his 16 August ruling, when he ruled that the Authority failed to comply with the requirements of Proposition 1A in two fundamental respects:  It was unable to certify completion of all the environmental clearances for the 300-mile Initial operating segment (IOS) extending from Merced to San Fernando Valley; and it was unable to identify "reasonably expected" sources of funds required to complete the Initial operating segment.

Related Content

  • March 31, 2016
    OCTA seeks proposals from three teams for I-405 freeway project
    The Orange County Transportation Authority, California, is seeking proposals from a shortlist of firms for the design and construction of the I-405 Improvement Project, an important step toward building a better freeway that is intended to improve travel times for those driving the corridor between Costa Mesa and the Los Angeles County line. The OCTA Board of Directors has unanimously approved the criteria for selecting a firm to design and build the freeway improvements and approved issuing the final re
  • July 23, 2015
    Jacobs JV awarded contract for California high speed rail
    The Jacobs Engineering Group has been awarded a contract to provide design services for the Construction Package 2-3 (CP 2-3) of the California High Speed Rail, the continuation of construction on the California high-speed rail system south towards Kern County. Jacobs is the lead designer for the Dragados-Flatiron joint venture for the design-build contract and is responsible for the infrastructure design. The California High Speed Rail is the first true high-speed rail being constructed in the United S
  • August 2, 2012
    Maturing photo enforcement gains legal status, public support
    In the US, affirmation of the photo traffic enforcement sector's legal status and rising public support were significant aspects of 2009. James Tuton, President and CEO of American Traffic Solutions, looks back over the year. In 2009, the photo traffic enforcement industry in North America continued to grow and mature, accompanied by increased public, legislative and legal scrutiny. While public support remains strong, we also saw increased attempts to undermine the industry by representatives of a small bu
  • January 20, 2012
    Infrastructure spending is an investment in economic recovery
    Transportation funding is caught in the crossfire as the President calls for infrastructure investment and a reinvigorated Republican majority in the House pushes back on federal spending. Andrew Bardin Williams reports. Every few months some politician or pundit declares that the country is on the verge of making the most important political decision in a generation. The 2006 mid-term election; the 2008 Presidential election; the passing of the stimulus bill; healthcare reform; the mania surrounding Tea Pa