Major setback for California bullet train

The California High-Speed Rail project, which aims to connect the mega-regions of the state, contribute to economic development and a cleaner environment, create jobs and preserve agricultural and protected lands, was dealt a serious blow when Judge Michael Kenny of the Sacramento Superior Court ruled that the California High-Speed Rail Authority "abused its discretion by approving a funding plan that did not comply with the requirements of the law."
August 27, 2013 Read time: 2 mins
The California High-Speed Rail project, which aims to connect the mega-regions of the state, contribute to economic development and a cleaner environment, create jobs and preserve agricultural and protected lands, was dealt a serious blow when Judge Michael Kenny of the Sacramento Superior Court ruled that the California High-Speed Rail Authority "abused its discretion by approving a funding plan that did not comply with the requirements of the law."

The judge agreed with Kings County officials who argued that there should be a full environmental impact report (EIR) for the first stretch of the line before any work can begin. While the authority is close to completing the EIR on the whole segment, the judge's more damning ruling was about funding: The initiative "required the Authority to identify sources of funds that were more than merely theoretically possible, but instead were reasonably expected to be actually available when needed," Kenny said in his ruling. "The state's business plan identifies only potential funding, without commitments, agreements or authorisations,” he said.

Kenny is allowing work to start on the train, which is already seriously delayed, but he scheduled future hearings to decide how the violations can be addressed.
By 2029, the train is projected to run from San Francisco to the Los Angeles basin in under three hours at speeds capable of over 200 miles per hour. The system will eventually extend to Sacramento and San Diego, totalling 800 miles with up to twenty-four stations. In addition, the Authority is working with regional partners to implement a state-wide rail modernisation plan that will invest billions of dollars in local and regional rail lines to meet the state’s 21st century transportation needs.

Related Content

  • Reflecting on five years of important ITS progress
    January 7, 2013
    Former head of the ITS Joint Program Office Shelley Row has passed the baton to a new director. Now working as an independent consultant, here she reflects on her five years at the helm of the JPO and what the future may hold for ITS in the US. During a mid-morning in Paris earlier this year, having just landed, I decided to take a trip on the city’s subway (Paris’ underground metro) into the city centre. A family with a small boy – about nine years old – boarded the same train. They were American and we st
  • How WiM helps authorities identify repeat offenders
    May 31, 2023
    Company profiling – the process of identifying repeat corporate offenders when it comes to things like truck overloading – is one of many uses of WiM. And it may become more important
  • LA Airport Metro Connector breaks ground
    July 5, 2021
    Project includes electric bus charging stations and is scheduled for 2024 completion
  • California DOT implements smart corridor
    October 14, 2013
    The California Department of Transportation (Caltrans) recently completed a smart corridor project on State Route 12 in Solano, Sacramento and San Joaquin counties, and I-5 in San Joaquin County. The project utilises intelligent transportation system (ITS) technology for five electronic message signs and four closed-circuit TV cameras to provide drivers with up to date travel information, enabling them to choose an alternate route in the event of congestion or roadway incidents.