Major setback for California bullet train

The California High-Speed Rail project, which aims to connect the mega-regions of the state, contribute to economic development and a cleaner environment, create jobs and preserve agricultural and protected lands, was dealt a serious blow when Judge Michael Kenny of the Sacramento Superior Court ruled that the California High-Speed Rail Authority "abused its discretion by approving a funding plan that did not comply with the requirements of the law."
August 27, 2013 Read time: 2 mins
The California High-Speed Rail project, which aims to connect the mega-regions of the state, contribute to economic development and a cleaner environment, create jobs and preserve agricultural and protected lands, was dealt a serious blow when Judge Michael Kenny of the Sacramento Superior Court ruled that the California High-Speed Rail Authority "abused its discretion by approving a funding plan that did not comply with the requirements of the law."

The judge agreed with Kings County officials who argued that there should be a full environmental impact report (EIR) for the first stretch of the line before any work can begin. While the authority is close to completing the EIR on the whole segment, the judge's more damning ruling was about funding: The initiative "required the Authority to identify sources of funds that were more than merely theoretically possible, but instead were reasonably expected to be actually available when needed," Kenny said in his ruling. "The state's business plan identifies only potential funding, without commitments, agreements or authorisations,” he said.

Kenny is allowing work to start on the train, which is already seriously delayed, but he scheduled future hearings to decide how the violations can be addressed.
By 2029, the train is projected to run from San Francisco to the Los Angeles basin in under three hours at speeds capable of over 200 miles per hour. The system will eventually extend to Sacramento and San Diego, totalling 800 miles with up to twenty-four stations. In addition, the Authority is working with regional partners to implement a state-wide rail modernisation plan that will invest billions of dollars in local and regional rail lines to meet the state’s 21st century transportation needs.

Related Content

  • Reducing injuries and deaths in US workzones shouldn’t be this complicated
    April 17, 2023
    In National Work Zone Awareness Week, surely the least we can do is to help get road workers home safely at the end of the day, says One.network's boss
  • Los Angeles County opts for Iteris bus signal priority
    November 6, 2013
    Building on multi-modal transit services provided over the past ten years, Iteris is to provide a multi-jurisdiction bus traffic signal priority system (BSP) for Torrance Transit’s Rapid Line in Los Angeles County, California. The US$2.2 million contract includes the design, procurement, deployment, and on-going operation and maintenance of a multi-jurisdiction BSP at 83 signalised intersections. The BSP system utilises existing on-bus systems that incorporate GPS-based automatic vehicle location equipme
  • How ITS weathers the storm on I-80
    September 7, 2021
    Weather-related closures on Wyoming’s I-80 can cost as much as $11.7m each. But a new initiative is harnessing V2X technology to prevent snow shutting things down
  • BMW i3 could ‘boost electric vehicle market’
    July 31, 2013
    According to Frost & Sullivan, BMW's ibrand could have a halo effect as did the Prius for Toyota. It could boost the market for electric vehicles which has had a slow uptake rate and also position BMW's brand as the most innovative premium OEM. Commenting on the launch of the new BMW i3, the electric supermini for sale in November, Frost & Sullivan said: "BMW is the first of the traditional premium manufacturers to take a leap of faith into the EV space with the i3. Like most car companies, BMW also sells 7