‘Formation flying’ engineering trains used to upgrade railway

In a bid to increase efficiencies and reduce delays for passengers, the UK’s Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete. The pioneering technique was used successfully at Sandy, Bedfordshire, on
February 16, 2017 Read time: 2 mins
In a bid to increase efficiencies and reduce delays for passengers, the UK’s 5021 Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete.

The pioneering technique was used successfully at Sandy, Bedfordshire, on a set of railway switches and crossings, which were being replaced as part of the Railway Upgrade Plan.

A pair of engineering trains were joined together connected by an umbilical and ran in parallel to simultaneously deliver tamping and dynamic track stabilisation (DTS) which simulated the equivalent of 200 trains passing over the tracks consecutively. Passenger trains were then able to start using the railway at speeds as high as 125mph as soon as the engineering team had finished because the track and ballast were firmly ‘bedded in’ – which meant Network Rail avoided thousands of pounds in compensation payments.

The news comes almost one year after Network Rail’s first successes with 125mph ‘high speed handbacks’ in January 2016 on regular plain line track. High speed handback ensures track is installed at each stage to its specific design tolerances, that care is taken while tamping to get the track to its final exact co-ordinates and that welding and stressing is completed as part of the core works.

Network Rail estimates that over US$6.2 million (£5 million) has already been saved by avoiding compensation payments since the start of the high speed handback programme.

For more information on companies in this article

Related Content

  • More Than: over half of Britons in test support car crash images used as speeding deterrent
    November 20, 2017
    58% of Britons who took part in a More Than (MT) visual deterrent speed sign test support its new proposal for speed limit signs to be accompanied by images of car crashes to deter drivers from speeding. The test follows a recent study from the campaign group, which revealed that 62% of drivers regularly ignore speeding signs along with 25% who stated that the threat of having to attend a speed awareness course isn't enough of a deterrent. Upon the reasons behind the effectiveness of the images in causing
  • Network Rail launches digital strategy to improve travel experience
    May 14, 2018
    Network Rail will carry out a digital railway strategy to help ensure that all new UK trains and signalling are digital or digital ready from 2019. The upgrade is aimed at improving the speed, punctuality and safety of the service. New digital rail technology will be utilised with the intention of allowing trains to run closer together and provide more frequent services. In addition, passengers are expected to be provided with improved mobile and WiFi connectivity. Train drivers will receive real-time
  • University develops rail crossing safety technology
    June 14, 2013
    Technology developed by Melbourne’s La Trobe University’s Centre for Technology Infusion that aims to reduce or even eliminate accidents at railway level crossings is to be trialled by the Queensland government as part of a $2 million commitment to address safety at rail crossings. The system uses GPS and dedicated short range communications (DSRC) wireless technology to establish a wireless connection between trains and vehicles approaching a railway crossing. The system is designed to detect the possibili
  • All aboard hyperloop 'by 2040 earliest', says Lux
    April 30, 2020
    Cost-per-mile estimates are rising and technical issues remain, says Lux Research