‘Formation flying’ engineering trains used to upgrade railway

In a bid to increase efficiencies and reduce delays for passengers, the UK’s Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete. The pioneering technique was used successfully at Sandy, Bedfordshire, on
February 16, 2017 Read time: 2 mins
In a bid to increase efficiencies and reduce delays for passengers, the UK’s 5021 Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete.

The pioneering technique was used successfully at Sandy, Bedfordshire, on a set of railway switches and crossings, which were being replaced as part of the Railway Upgrade Plan.

A pair of engineering trains were joined together connected by an umbilical and ran in parallel to simultaneously deliver tamping and dynamic track stabilisation (DTS) which simulated the equivalent of 200 trains passing over the tracks consecutively. Passenger trains were then able to start using the railway at speeds as high as 125mph as soon as the engineering team had finished because the track and ballast were firmly ‘bedded in’ – which meant Network Rail avoided thousands of pounds in compensation payments.

The news comes almost one year after Network Rail’s first successes with 125mph ‘high speed handbacks’ in January 2016 on regular plain line track. High speed handback ensures track is installed at each stage to its specific design tolerances, that care is taken while tamping to get the track to its final exact co-ordinates and that welding and stressing is completed as part of the core works.

Network Rail estimates that over US$6.2 million (£5 million) has already been saved by avoiding compensation payments since the start of the high speed handback programme.

For more information on companies in this article

Related Content

  • Cellular coverage on trains to get boost
    October 2, 2013
    According to Ingo Flomer, director of Product Management of UK company Axell Wireless, UK transport secretary Patrick McLoughlin’s intention to upgrade the rail network to enable passengers to access high-speed mobile broadband does not go far enough to promote an integrated communications infrastructure that supports cellular (3G and 4G) coverage on-board trains. Flomer says the UK has significant technological hurdles to overcome to connect rail passengers to the cellular network. The coverage would ha
  • Ontario partners with Thales Canada to deliver rail signalling project
    April 14, 2016
    The province of Ontario is partnering with Thales Canada, a subsidiary of France-based Thales Group, to develop the next generation of rail signalling solutions for the province’s railways. Ontario, which is home to almost half of Canada’s full time R&D personnel, will invest up to US$9.4 million (CA$12 million) through the Jobs and Prosperity Fund with the overall project investment value set to reach approximately US$62.5 million (CA$80 million). Ontario, which spends more than US$11 billion (CA$14 bi
  • Dynamic Message Signs : Don’t replace, refurbish and upgrade
    August 12, 2015
    Refurbishing old dynamic message signs can save money and increase technical capabilities as David Crawford discovers. Evidence is growing on both sides of the Atlantic of the scope for retrofitting old or technically out-of-date dynamic message signs (DMS) with new electronic equipment, to save on the costs of installing full-scale replacements. In the last four months of 2014, a number of US states progressed programmes that achieved savings of more than US$1.75 million (€1.56million).
  • '190,000 trips' on day 1 of Sydney Metro extension
    August 20, 2024
    15.5km extension means 2,645 new metro services will travel through city each week