‘Formation flying’ engineering trains used to upgrade railway

In a bid to increase efficiencies and reduce delays for passengers, the UK’s Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete. The pioneering technique was used successfully at Sandy, Bedfordshire, on
February 16, 2017 Read time: 2 mins
In a bid to increase efficiencies and reduce delays for passengers, the UK’s 5021 Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete.

The pioneering technique was used successfully at Sandy, Bedfordshire, on a set of railway switches and crossings, which were being replaced as part of the Railway Upgrade Plan.

A pair of engineering trains were joined together connected by an umbilical and ran in parallel to simultaneously deliver tamping and dynamic track stabilisation (DTS) which simulated the equivalent of 200 trains passing over the tracks consecutively. Passenger trains were then able to start using the railway at speeds as high as 125mph as soon as the engineering team had finished because the track and ballast were firmly ‘bedded in’ – which meant Network Rail avoided thousands of pounds in compensation payments.

The news comes almost one year after Network Rail’s first successes with 125mph ‘high speed handbacks’ in January 2016 on regular plain line track. High speed handback ensures track is installed at each stage to its specific design tolerances, that care is taken while tamping to get the track to its final exact co-ordinates and that welding and stressing is completed as part of the core works.

Network Rail estimates that over US$6.2 million (£5 million) has already been saved by avoiding compensation payments since the start of the high speed handback programme.

Related Content

  • December 16, 2014
    Growing passenger numbers, fare rises for UK rail
    According to Rail Travel, a new market report from business intelligence provider Key Note, in 2013/2014 the total value of passenger receipts for UK rail travel increased by 6.2 per cent year-on-year, and grew by 32.5 per cent over a five-year period. In addition, passenger journeys grew by 23.5 per cent over the five-year review period, with passenger kilometres travelled also growing by 17.9 per cent over the same timeframe. For the purpose of this report, the rail industry in the UK has been split in
  • June 17, 2016
    Brooklyn eyes Bogota’s BRT system
    David Crawford considers the increased interest in bus rapid transit and looks that the latest trends. Bus rapid transit (BRT) is gaining an increasingly high profile in the US public transport agenda, for two main reasons. One is the potential for ‘trains on wheels’ to save substantially on installation costs as compared with other modes such as underground metros or light-rail transit. Another, highlighted in the case of New York City, is the value of having a rapid surface-based alternative available whe
  • January 13, 2014
    Maryland to implement positive train control
    In the wake of the December derailment of a New York passenger train that came off the tracks as it sped too fast into a turn, the Maryland Board of Public Works has approved a US$13 million contract to begin installing positive train control equipment, which uses GPS and radio signalling to react automatically if a collision or derailment is anticipated.
  • August 23, 2023
    The inside story of how traffic chaos was avoided after I-95 collapse
    June’s collapse of major US roadway I-95 in Pennsylvania could have caused lengthy traffic chaos. But - relatively speaking at least - it didn’t and gridlock was avoided. Alan Dron finds out why