‘Formation flying’ engineering trains used to upgrade railway

In a bid to increase efficiencies and reduce delays for passengers, the UK’s Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete. The pioneering technique was used successfully at Sandy, Bedfordshire, on
February 16, 2017 Read time: 2 mins
In a bid to increase efficiencies and reduce delays for passengers, the UK’s 5021 Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete.

The pioneering technique was used successfully at Sandy, Bedfordshire, on a set of railway switches and crossings, which were being replaced as part of the Railway Upgrade Plan.

A pair of engineering trains were joined together connected by an umbilical and ran in parallel to simultaneously deliver tamping and dynamic track stabilisation (DTS) which simulated the equivalent of 200 trains passing over the tracks consecutively. Passenger trains were then able to start using the railway at speeds as high as 125mph as soon as the engineering team had finished because the track and ballast were firmly ‘bedded in’ – which meant Network Rail avoided thousands of pounds in compensation payments.

The news comes almost one year after Network Rail’s first successes with 125mph ‘high speed handbacks’ in January 2016 on regular plain line track. High speed handback ensures track is installed at each stage to its specific design tolerances, that care is taken while tamping to get the track to its final exact co-ordinates and that welding and stressing is completed as part of the core works.

Network Rail estimates that over US$6.2 million (£5 million) has already been saved by avoiding compensation payments since the start of the high speed handback programme.

Related Content

  • April 10, 2014
    Cellint measures speed and travel time without roadside infrastructure
    Collecting speed and travel time data without using roadside infrastructure could offer new possibilities to cash-strapped road authorities. Streaming video may be useful for traffic controllers to monitor incidents and automatic number plate recognition may be required for enforcement, but neither are necessary for many ITS functions. For instance travel times, tailbacks, percentage of vehicles turning, origin and destination analysis can all be done using Bluetooth and/or WI-Fi sensors and without video o
  • October 24, 2014
    CARTES 2014 where ‘users on the move’ is the central theme
    A message from Isabelle Alfano, Exhibition Director, CARTES Network ‘Users on the move’ is the central theme of this year’s show. A great number of services, devices and systems are built around a new way of life made to fit users’ mobility.
  • June 4, 2013
    Further EIB support for Lithuanian Railways
    Lithuanian Railways are set to benefit from new rolling stock following a US$65.3 million loan agreement with the European Investment Bank (EIB). After the support for the upgrading of railway infrastructure and purchase of new locomotives, this is now the third EIB operation aimed at modernising Lithuanian railways. “The EIB strongly promotes sustainable transport, and railways will remain one of the most energy-efficient and least polluting land transport modes. We therefore particularly welcome this agre
  • December 6, 2016
    Bombardier to supply 52 additional commuter trains to French railways
    Rail technology specialist Bombardier Transportation is to supply French national railway company, Société Nationale des Chemins de fer Français (SNCF) with 52 additional Francilien electric multiple unit (EMU) commuter trains. The order, financed by Île-de-France's transport authority Syndicat des transports d'Île-de-France (STIF), is valued at approximately US$370 (€348 million) and is a call off from a contract signed in 2006 with SNCF for a maximum of 372 trains. The first trains from this order will