‘Formation flying’ engineering trains used to upgrade railway

In a bid to increase efficiencies and reduce delays for passengers, the UK’s Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete. The pioneering technique was used successfully at Sandy, Bedfordshire, on
February 16, 2017 Read time: 2 mins
In a bid to increase efficiencies and reduce delays for passengers, the UK’s 5021 Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete.

The pioneering technique was used successfully at Sandy, Bedfordshire, on a set of railway switches and crossings, which were being replaced as part of the Railway Upgrade Plan.

A pair of engineering trains were joined together connected by an umbilical and ran in parallel to simultaneously deliver tamping and dynamic track stabilisation (DTS) which simulated the equivalent of 200 trains passing over the tracks consecutively. Passenger trains were then able to start using the railway at speeds as high as 125mph as soon as the engineering team had finished because the track and ballast were firmly ‘bedded in’ – which meant Network Rail avoided thousands of pounds in compensation payments.

The news comes almost one year after Network Rail’s first successes with 125mph ‘high speed handbacks’ in January 2016 on regular plain line track. High speed handback ensures track is installed at each stage to its specific design tolerances, that care is taken while tamping to get the track to its final exact co-ordinates and that welding and stressing is completed as part of the core works.

Network Rail estimates that over US$6.2 million (£5 million) has already been saved by avoiding compensation payments since the start of the high speed handback programme.

Related Content

  • September 25, 2017
    Government invests in northern digital railway plans to improve trans-Pennine
    The UK government is developing plans for Britain’s first digital intercity railway in the north, as it invests US$17.5 billion (£13 billion) in improving journeys across the region. The UK government is developing plans for Britain’s first digital intercity railway in the north, as it invests US$17.5 billion (£13 billion) in improving journeys across the region.
  • December 21, 2015
    Measuring alertness to avert drowsy driver incidents
    Falling asleep at the wheel is the primary cause in thousands of deaths on American and other roads, with truck drivers the most at-risk group. David Crawford investigates measures to counter drowsy driving.
  • January 23, 2012
    Future traffic management needs new thinking, new technology
    One of the biggest problems facing US ITS professionals, says Georgia DOT's Hugh Colton, is the constrained thinking which is sometimes forced upon those making procurement decisions. It is time, he says, to look again at how we do things. In the November/December 2010 edition of this journal, Pete Goldin interviewed Joseph Sussman, chairman of the US's ITS Program Advisory Committee. Amongst other observations that Sussman made was that, technologically, ITS in the US is 10 years behind that in the world-l
  • September 7, 2015
    EBRD connects Kosovo to European Railway network
    The European Bank for Reconstruction and Development (EBRD) is providing a senior loan of US$44.5 million to finance the modernisation of Kosovo’s railway infrastructure, deepening regional integration and strengthening the country’s economic development. The loan to Infrastruktura e Hekurudhave të Kosovës (Infrakos), the national railway infrastructure company, will provide funding to upgrade Kosovo’s only international rail link, Rail Route 10. The 148 kilometre-long line is divided into three section