‘Formation flying’ engineering trains used to upgrade railway

In a bid to increase efficiencies and reduce delays for passengers, the UK’s Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete. The pioneering technique was used successfully at Sandy, Bedfordshire, on
February 16, 2017 Read time: 2 mins
In a bid to increase efficiencies and reduce delays for passengers, the UK’s 5021 Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete.

The pioneering technique was used successfully at Sandy, Bedfordshire, on a set of railway switches and crossings, which were being replaced as part of the Railway Upgrade Plan.

A pair of engineering trains were joined together connected by an umbilical and ran in parallel to simultaneously deliver tamping and dynamic track stabilisation (DTS) which simulated the equivalent of 200 trains passing over the tracks consecutively. Passenger trains were then able to start using the railway at speeds as high as 125mph as soon as the engineering team had finished because the track and ballast were firmly ‘bedded in’ – which meant Network Rail avoided thousands of pounds in compensation payments.

The news comes almost one year after Network Rail’s first successes with 125mph ‘high speed handbacks’ in January 2016 on regular plain line track. High speed handback ensures track is installed at each stage to its specific design tolerances, that care is taken while tamping to get the track to its final exact co-ordinates and that welding and stressing is completed as part of the core works.

Network Rail estimates that over US$6.2 million (£5 million) has already been saved by avoiding compensation payments since the start of the high speed handback programme.

Related Content

  • December 14, 2015
    Milestone for Northern Powerhouse as UK’s first tram train unveiled
    The UK's first ever tram train has been unveiled in South Yorkshire. Vehicles from this government-funded project are designed to run on both the city’s tramlines and the rail network between Sheffield and Rotherham. This will allow passengers to make single journey between tram stops and conventional rail stations from early 2017, once the works are complete. Prior to this, the tram trains will undergo a period of testing, before being introduced on the Supertram network in summer 2016, to provide extra
  • July 28, 2015
    Hitachi Rail Europe wins UK first traffic management contract
    Passengers on some of the busiest commuter lines in the UK can look forward to more frequent and more reliable trains following a deal to provide new traffic management technology on the Thameslink route through central London. Network Rail and the Thameslink Programme have signed a contract with Hitachi Rail Europe (HRE) to deliver a step-change in technology through state-of-the-art traffic management technology.
  • February 23, 2017
    LiDAR sets its sights on future problems
    AAdvances in LiDAR are helping transport authorities improve services and identify potential problem areas, as geospatial technology expert Dr Neil Slatcher explains. The effects of climate change on the transport infrastructure have long been a cause of concern within the transportation sector - and not only on the structures themselves but also on the surrounding areas. This year, those concerns have become reality with landslides, structural collapses and surfacing issues impacting services across the wo
  • April 15, 2015
    EU to fund common train control system
    The EU's TEN-T Programme is to provide funding of over US$16 million for the development and installation of the common European Train Control System (ETCS) in Belgium, Luxembourg, Denmark and the UK. The new system is expected to improve the interoperability, safety, reliability and capacity on European railways. Seven separate projects aim to contribute to the deployment of the European Rail Traffic Management System (ERTMS) in the EU and enhance interoperability of European rail services. While increa