‘Formation flying’ engineering trains used to upgrade railway

In a bid to increase efficiencies and reduce delays for passengers, the UK’s Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete. The pioneering technique was used successfully at Sandy, Bedfordshire, on
February 16, 2017 Read time: 2 mins
In a bid to increase efficiencies and reduce delays for passengers, the UK’s 5021 Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete.

The pioneering technique was used successfully at Sandy, Bedfordshire, on a set of railway switches and crossings, which were being replaced as part of the Railway Upgrade Plan.

A pair of engineering trains were joined together connected by an umbilical and ran in parallel to simultaneously deliver tamping and dynamic track stabilisation (DTS) which simulated the equivalent of 200 trains passing over the tracks consecutively. Passenger trains were then able to start using the railway at speeds as high as 125mph as soon as the engineering team had finished because the track and ballast were firmly ‘bedded in’ – which meant Network Rail avoided thousands of pounds in compensation payments.

The news comes almost one year after Network Rail’s first successes with 125mph ‘high speed handbacks’ in January 2016 on regular plain line track. High speed handback ensures track is installed at each stage to its specific design tolerances, that care is taken while tamping to get the track to its final exact co-ordinates and that welding and stressing is completed as part of the core works.

Network Rail estimates that over US$6.2 million (£5 million) has already been saved by avoiding compensation payments since the start of the high speed handback programme.

For more information on companies in this article

Related Content

  • Value of time – the key decider
    March 4, 2014
    The ‘value of time’ concept can be a vital decider in prioritising transport projects, as Lorenzo Casullo and Serbjeet Kohli of Steer Davies Gleave explain. How much do travellers value their time and how much would they be willing to pay for a better and faster transport option? For many years Steer Davies Gleave (SDG) has been collecting this type of information from thousands of people across the world as it researches travellers’ behaviour. And given the importance of this parameter for transport mo
  • Florida SunTrax centre wins top IBTTA award
    September 16, 2020
    Florida's Turnpike Enterprise R&D facility has four toll sites for testing
  • Mayor’s lane rental scheme cuts roadwork disruption
    April 11, 2014
    A new study into London’s lane rental scheme shows that since its introduction the amount of serious and severe disruption caused by planned roadworks has been cut by 46 per cent on the capital’s busiest roads, reducing delays for all road users. The scheme, which came into effect in June 2012 on the busiest parts of London’s road network, is designed to encourage utility companies to avoid digging up the busiest roads at peak traffic times. Following the introduction of the scheme, around 90 per cent of
  • Changing driving conditions need ongoing driver training
    January 23, 2012
    Trevor Ellis, chairman of the ITS UK Enforcement Interest Group, considers the role of ongoing driver training in increasing compliance. It is over 30 years since I passed my driving test. The world was quite a different place then, in that there were only half the vehicles there are now on the UK's roads, mobile phones did not really exist and (in the UK at least) the vast majority of us drove cars which by today's standards exhibited dreadful dynamic stability and were woefully underpowered.