‘Formation flying’ engineering trains used to upgrade railway

In a bid to increase efficiencies and reduce delays for passengers, the UK’s Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete. The pioneering technique was used successfully at Sandy, Bedfordshire, on
February 16, 2017 Read time: 2 mins
In a bid to increase efficiencies and reduce delays for passengers, the UK’s 5021 Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete.

The pioneering technique was used successfully at Sandy, Bedfordshire, on a set of railway switches and crossings, which were being replaced as part of the Railway Upgrade Plan.

A pair of engineering trains were joined together connected by an umbilical and ran in parallel to simultaneously deliver tamping and dynamic track stabilisation (DTS) which simulated the equivalent of 200 trains passing over the tracks consecutively. Passenger trains were then able to start using the railway at speeds as high as 125mph as soon as the engineering team had finished because the track and ballast were firmly ‘bedded in’ – which meant Network Rail avoided thousands of pounds in compensation payments.

The news comes almost one year after Network Rail’s first successes with 125mph ‘high speed handbacks’ in January 2016 on regular plain line track. High speed handback ensures track is installed at each stage to its specific design tolerances, that care is taken while tamping to get the track to its final exact co-ordinates and that welding and stressing is completed as part of the core works.

Network Rail estimates that over US$6.2 million (£5 million) has already been saved by avoiding compensation payments since the start of the high speed handback programme.

For more information on companies in this article

Related Content

  • Digital twins promise no jam tomorrow
    June 6, 2024
    Every year, Transport for London helps make billions of road journeys congestion-free - but could it do better? Digital twin and graph technology are starting to make London less congested and greener, says database expert Aaron Holt
  • Connected vehicle trials get big backing from USDOT
    March 14, 2016
    Connected vehicle technology will emerge as a sustainable reality at three sites in the US over the next four years. Jon Masters reports. Advocates of connected vehicle (CV) technology have received a welcome boost from news that the US government has committed a further $4 billion towards automated vehicle research and CV technology. This comes hot on the heels of the US Department of Transportation’s $42 million CV pilot pledge in October last year.
  • Cincoze focuses on rail transit safety
    October 6, 2021
    New product can be paired with the PoE CFM module, allowing for future upgrades
  • Transmax trials emergency vehicle ‘green wave’
    December 6, 2013
    Existing equipment used in Australian emergency vehicle ‘green wave’ trial. Despite the lights and sirens, accidents between the motoring public and emergency vehicles on their way to/from the scene of an incident are relatively frequent. Figures from various sources indicate that road accidents are the second most frequent cause of death for on-duty fire fighter fatalities and that more than 90% of ambulance and fire engine accidents occur when the lights are on and the sirens wailing. Other studies indica