‘Formation flying’ engineering trains used to upgrade railway

In a bid to increase efficiencies and reduce delays for passengers, the UK’s Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete. The pioneering technique was used successfully at Sandy, Bedfordshire, on
February 16, 2017 Read time: 2 mins
In a bid to increase efficiencies and reduce delays for passengers, the UK’s 5021 Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete.

The pioneering technique was used successfully at Sandy, Bedfordshire, on a set of railway switches and crossings, which were being replaced as part of the Railway Upgrade Plan.

A pair of engineering trains were joined together connected by an umbilical and ran in parallel to simultaneously deliver tamping and dynamic track stabilisation (DTS) which simulated the equivalent of 200 trains passing over the tracks consecutively. Passenger trains were then able to start using the railway at speeds as high as 125mph as soon as the engineering team had finished because the track and ballast were firmly ‘bedded in’ – which meant Network Rail avoided thousands of pounds in compensation payments.

The news comes almost one year after Network Rail’s first successes with 125mph ‘high speed handbacks’ in January 2016 on regular plain line track. High speed handback ensures track is installed at each stage to its specific design tolerances, that care is taken while tamping to get the track to its final exact co-ordinates and that welding and stressing is completed as part of the core works.

Network Rail estimates that over US$6.2 million (£5 million) has already been saved by avoiding compensation payments since the start of the high speed handback programme.

For more information on companies in this article

Related Content

  • A future vision for transport in Wales
    November 13, 2014
    A new report by the Chartered Institute of Logistics and Transport (CILT) Cymru Wales, Vision 2035: Cymru Wales, looks to the future and visualises how transport and logistics in Wales would develop, taking account of population changes, technological developments and social and political change. By 2035, Wales will be making decisions on all aspects of transport, including air passenger duty, rail franchising and road policy. There will also be greater government involvement in public transport operatio
  • AVs need extreme training, says research
    May 24, 2022
    AVs will be safer if they are given 'one-in-a-million' collision risk scenarios to learn from
  • Mexico issues rail tender
    March 5, 2014
    Mexico's transport and communications ministry (SCT) has launched a tender for construction of the Mexico City-Toluca passenger rail line. The project will be divided into a series of separate tenders, with the first open to Mexican companies only. The tender launched on 28 February is a public works contract for construction of the first 36km of railway. Subsequent tenders will relate to the acquisition of rolling stock and electromechanical works. The electric trains will travel at speeds of up to 1
  • Putting a stop to intersection indecision
    March 9, 2015
    David Crawford takes a look at innovations to reduce crashes at rural intersections. Intersection crashes continue to represent a worryingly large share of deaths and serious injuries across US highway networks. Statistics from the US Department of Transportation’s Federal Highway Administration show that an average of 21% of road traffic accident deaths occur at crossings. The National Highway Traffic Safety Administration (NHTSA) calculates that intersection crashes account for 48% of all injury-related i