‘Formation flying’ engineering trains used to upgrade railway

In a bid to increase efficiencies and reduce delays for passengers, the UK’s Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete. The pioneering technique was used successfully at Sandy, Bedfordshire, on
February 16, 2017 Read time: 2 mins
In a bid to increase efficiencies and reduce delays for passengers, the UK’s 5021 Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete.

The pioneering technique was used successfully at Sandy, Bedfordshire, on a set of railway switches and crossings, which were being replaced as part of the Railway Upgrade Plan.

A pair of engineering trains were joined together connected by an umbilical and ran in parallel to simultaneously deliver tamping and dynamic track stabilisation (DTS) which simulated the equivalent of 200 trains passing over the tracks consecutively. Passenger trains were then able to start using the railway at speeds as high as 125mph as soon as the engineering team had finished because the track and ballast were firmly ‘bedded in’ – which meant Network Rail avoided thousands of pounds in compensation payments.

The news comes almost one year after Network Rail’s first successes with 125mph ‘high speed handbacks’ in January 2016 on regular plain line track. High speed handback ensures track is installed at each stage to its specific design tolerances, that care is taken while tamping to get the track to its final exact co-ordinates and that welding and stressing is completed as part of the core works.

Network Rail estimates that over US$6.2 million (£5 million) has already been saved by avoiding compensation payments since the start of the high speed handback programme.

For more information on companies in this article

Related Content

  • Nearly 59,000 US bridges still structurally deficient, new analysis finds
    February 19, 2016
    According to the US Department of Transportation's recently-released 2015 National Bridge Inventory database, there were 2,574 fewer structurally deficient bridges in 2015 compared to the number in 2014. However, there are still 58,500 on the structurally deficient list and at the current pace of bridge investment it would take at least 21 years before they were all replaced or upgraded. The American Road & Transportation Builders Association (ARTBA), which conducts an annual review of state bridge da
  • New clean diesel technology improving air quality and fuel efficiency, research finds
    July 29, 2016
    The introduction of more advanced diesel truck engines, innovative emissions control systems, and cleaner diesel fuel over the past decade have successfully resulted in major improvements in air quality and fuel efficiency, according to new research compiled by The Martec Group, a global technical marketing research firm, for the Diesel Technology Forum. The four million cleaner heavy-duty diesels introduced from 2007 through 2015 have saved US consumers: 29 million tonnes of C02; 7.5 million tonnes o
  • Automating seat belt compliance a priority for road safety
    February 2, 2012
    Finland's VTT is developing a mobile, automated seatbelt compliance system. Here, the organisation's Matti Kutila discusses progress
  • The weighty problem of truck routing enforcement
    March 17, 2015
    The growing impact of heavy commercial vehicles on urban and interurban highway infrastructures around the world is driving the need for reliable route access restriction and monitoring. The support role of enforcement is proving fertile ground for ITS development. Bridges are especially vulnerable – and critical in terms of travel delays. The US state of Oregon’s Department of Transportation (ODOT) operates what it claims is one of the country’s most aggressive truck route restriction enforcement programme