‘Formation flying’ engineering trains used to upgrade railway

In a bid to increase efficiencies and reduce delays for passengers, the UK’s Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete. The pioneering technique was used successfully at Sandy, Bedfordshire, on
February 16, 2017 Read time: 2 mins
In a bid to increase efficiencies and reduce delays for passengers, the UK’s 5021 Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete.

The pioneering technique was used successfully at Sandy, Bedfordshire, on a set of railway switches and crossings, which were being replaced as part of the Railway Upgrade Plan.

A pair of engineering trains were joined together connected by an umbilical and ran in parallel to simultaneously deliver tamping and dynamic track stabilisation (DTS) which simulated the equivalent of 200 trains passing over the tracks consecutively. Passenger trains were then able to start using the railway at speeds as high as 125mph as soon as the engineering team had finished because the track and ballast were firmly ‘bedded in’ – which meant Network Rail avoided thousands of pounds in compensation payments.

The news comes almost one year after Network Rail’s first successes with 125mph ‘high speed handbacks’ in January 2016 on regular plain line track. High speed handback ensures track is installed at each stage to its specific design tolerances, that care is taken while tamping to get the track to its final exact co-ordinates and that welding and stressing is completed as part of the core works.

Network Rail estimates that over US$6.2 million (£5 million) has already been saved by avoiding compensation payments since the start of the high speed handback programme.

For more information on companies in this article

Related Content

  • Asecap debates the future of tolling
    August 23, 2016
    Colin Sowman reports form Asecap’s Study & Information Days event in Madrid. At Asecap’s (the Association of European Toll Road Operators) recent Study and Information Days event there was no doubt about the subject at the top of the agenda: the European Union Directive 23/2014/EU. This will introduce fundamental changes to the concession model under which Asecap members operate more than 50,000km of tolled highways and, in response, it has compiled a report entitled Proposal for a Sustainable Concession Mo
  • Move to modernise London underground leads to strikes
    February 5, 2014
    A move by Transport for London (TfL) to modernise the London Underground, including the loss of 950 jobs and the closure of all ticket offices has led to the widespread strikes currently being experienced by travellers. The National Union of Rail, Maritime and Transport Workers (RMT) has called for the withdrawal of the cuts, saying that the plans are discriminatory and would leave important groups of staff vulnerable to abuse and assault as enforced lone working is pushed through. TfL claims the meas
  • London invests in bus priority schemes to help keep bus passengers moving
    January 26, 2016
    With London’s roads seeing an increase in congestion due to a construction boom and a significant growth in population, Transport for London is investing heavily in helping keep the roads moving through a range of means. Part of this programme is designed to help buses get through congested areas quicker and more reliably. A US$284 million investment in new bus priority schemes in the capital includes changes to road layouts and junctions and enabling small changes to routes so that buses can avoid traff
  • KeolisAmey reappointed to operate London's automated rail system
    October 7, 2024
    New eight-year €140m deal from Transport for London to run Docklands Light Railway