‘Formation flying’ engineering trains used to upgrade railway

In a bid to increase efficiencies and reduce delays for passengers, the UK’s Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete. The pioneering technique was used successfully at Sandy, Bedfordshire, on
February 16, 2017 Read time: 2 mins
In a bid to increase efficiencies and reduce delays for passengers, the UK’s 5021 Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete.

The pioneering technique was used successfully at Sandy, Bedfordshire, on a set of railway switches and crossings, which were being replaced as part of the Railway Upgrade Plan.

A pair of engineering trains were joined together connected by an umbilical and ran in parallel to simultaneously deliver tamping and dynamic track stabilisation (DTS) which simulated the equivalent of 200 trains passing over the tracks consecutively. Passenger trains were then able to start using the railway at speeds as high as 125mph as soon as the engineering team had finished because the track and ballast were firmly ‘bedded in’ – which meant Network Rail avoided thousands of pounds in compensation payments.

The news comes almost one year after Network Rail’s first successes with 125mph ‘high speed handbacks’ in January 2016 on regular plain line track. High speed handback ensures track is installed at each stage to its specific design tolerances, that care is taken while tamping to get the track to its final exact co-ordinates and that welding and stressing is completed as part of the core works.

Network Rail estimates that over US$6.2 million (£5 million) has already been saved by avoiding compensation payments since the start of the high speed handback programme.

For more information on companies in this article

Related Content

  • ITS homes in on cycling safety
    April 9, 2014
    A new generation of ITS equipment is helping road authorities get to grips with cycle safety – and not a moment too soon as Colin Sowman discovers. Cyclists - remember them? Apparently not. At least not according to the OECD 2013 report Cycling, Health and Safety which contains the statement: ‘Cyclists are often forgotten in the design of the road traffic system’. Looking through the statistics that exist (each country appears to compile them differently) it is not difficult to see how such a conclusion cou
  • Big event traffic management: Taylor's Version
    February 28, 2025
    StreetLight crunches Swifties numbers on US Eras Tour to find a clear winner
  • Reducing climate impacts starts at the intersection, says Inrix
    September 11, 2023
    The tools to identify and reduce unnecessary delays at intersections are here – and traffic signal performance improvement is also eligible for US government funding, points out Rick Schuman of Inrix
  • Report: Priority funding for rail projects drives investments in Turkey
    January 22, 2015
    Turkish railways have undergone a complete overhaul due to significant investments over the last five years. In the majority of rail projects currently under way, investment is directed towards the construction of new high-speed rail (HSR) lines, electrification, extensions and upgrading of existing infrastructure. With u$18 billion allocated for the rail sector as part of the Turkey Vision 2023 plan, the country is expected to have a total conventional rail network length of 25,940 kilometres and a HSR net