‘Formation flying’ engineering trains used to upgrade railway

In a bid to increase efficiencies and reduce delays for passengers, the UK’s Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete. The pioneering technique was used successfully at Sandy, Bedfordshire, on
February 16, 2017 Read time: 2 mins
In a bid to increase efficiencies and reduce delays for passengers, the UK’s 5021 Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete.

The pioneering technique was used successfully at Sandy, Bedfordshire, on a set of railway switches and crossings, which were being replaced as part of the Railway Upgrade Plan.

A pair of engineering trains were joined together connected by an umbilical and ran in parallel to simultaneously deliver tamping and dynamic track stabilisation (DTS) which simulated the equivalent of 200 trains passing over the tracks consecutively. Passenger trains were then able to start using the railway at speeds as high as 125mph as soon as the engineering team had finished because the track and ballast were firmly ‘bedded in’ – which meant Network Rail avoided thousands of pounds in compensation payments.

The news comes almost one year after Network Rail’s first successes with 125mph ‘high speed handbacks’ in January 2016 on regular plain line track. High speed handback ensures track is installed at each stage to its specific design tolerances, that care is taken while tamping to get the track to its final exact co-ordinates and that welding and stressing is completed as part of the core works.

Network Rail estimates that over US$6.2 million (£5 million) has already been saved by avoiding compensation payments since the start of the high speed handback programme.

For more information on companies in this article

Related Content

  • Coronavirus: World’s transit system moves into lockdown
    March 20, 2020
    The threat of coronavirus is plunging the world’s transit systems into lockdown as ridership numbers dwindle and limited services become the norm.
  • Voi expands e-scooter operations
    November 11, 2020
    Voi is hoping to save between 88 to 196 tonnes of CO2 eq in the region
  • Land of ITS opportunities
    February 2, 2012
    Geographically, Russia, the largest country in the world, is vast. So too are the opportunities for the global ITS community, which is why ITS Russia has been actively promoting the country and the opportunities that abound there. ITS Russia is reaching out around the world. In October, at the 17th ITS World Congress in Busan, South Korea, a cooperative agreement was signed with ITS America to promote and strengthen research, educational, and commercial cooperation in the ITS field among the two association
  • Land of ITS opportunities
    February 6, 2012
    Geographically, Russia, the largest country in the world, is vast. So too are the opportunities for the global ITS community, which is why ITS Russia has been actively promoting the country and the opportunities that abound there