‘Formation flying’ engineering trains used to upgrade railway

In a bid to increase efficiencies and reduce delays for passengers, the UK’s Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete. The pioneering technique was used successfully at Sandy, Bedfordshire, on
February 16, 2017 Read time: 2 mins
In a bid to increase efficiencies and reduce delays for passengers, the UK’s 5021 Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete.

The pioneering technique was used successfully at Sandy, Bedfordshire, on a set of railway switches and crossings, which were being replaced as part of the Railway Upgrade Plan.

A pair of engineering trains were joined together connected by an umbilical and ran in parallel to simultaneously deliver tamping and dynamic track stabilisation (DTS) which simulated the equivalent of 200 trains passing over the tracks consecutively. Passenger trains were then able to start using the railway at speeds as high as 125mph as soon as the engineering team had finished because the track and ballast were firmly ‘bedded in’ – which meant Network Rail avoided thousands of pounds in compensation payments.

The news comes almost one year after Network Rail’s first successes with 125mph ‘high speed handbacks’ in January 2016 on regular plain line track. High speed handback ensures track is installed at each stage to its specific design tolerances, that care is taken while tamping to get the track to its final exact co-ordinates and that welding and stressing is completed as part of the core works.

Network Rail estimates that over US$6.2 million (£5 million) has already been saved by avoiding compensation payments since the start of the high speed handback programme.

For more information on companies in this article

Related Content

  • V2X: The design challenges
    May 2, 2018
    The connected future throws up a number of enticing possibilities for us all. But, says Houman Zarrinkoub of MathWorks, issues around visualisation, prototyping and model evolution need to be examined carefully. We are all aware of the huge amount of investment going into driverless car technologies. With the likes of Volvo, Tesla and BMW getting in on the act, soon they will be a common sight on our roads. However, for this to occur, the vehicles must be able to connect with each other and ensure driver
  • Caltrans takes the long view of transport
    October 21, 2016
    Caltrans’ Malcolm Dougherty took time out of his schedule at ITS America 2016 in San Jose to talk to ITS International about current and future challenges. As director of California Department of Transportation (Caltrans) since mid-2012, many would say that Malcolm Dougherty has one of the best jobs in transportation. Caltrans is one of the most progressive and innovative transport authorities, implementing policies to encourage cycling, piloting new
  • Pricing practise for HOT lane operation
    May 11, 2017
    Timothy Compston weighs up the critical elements that keep the wheels of dynamic pricing schemes turning in today's high-occupancy toll (HOT) lanes. In the drive towards smarter tolling it is perhaps not surprising that sophisticated pricing algorithms are being rolled out to better reflect supply and demand on the roadway. This is the case with high-occupancy toll (HOT) lanes which a growing number of DoTs are seeing as a way of smoothing the operation of their existing, and planned, freeway infrastructure
  • Kapsch CarrierCom to implement railway communication network in Luxembourg
    March 30, 2016
    Luxembourg’s national railway operator CFL has awarded Kapsch CarrierCom the contract to implement a countrywide railway communication network based on GSM-R (Global System for Mobile Communications – Railway) for the country’s railway network. The contract, which is scheduled to be complete at the beginning of 2017, includes operation and service support for the first three years. Kapsch will be installing an end-to-end railway telecommunication network based on the GSM-R standard, including a modern IP