‘Formation flying’ engineering trains used to upgrade railway

In a bid to increase efficiencies and reduce delays for passengers, the UK’s Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete. The pioneering technique was used successfully at Sandy, Bedfordshire, on
February 16, 2017 Read time: 2 mins
In a bid to increase efficiencies and reduce delays for passengers, the UK’s 5021 Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete.

The pioneering technique was used successfully at Sandy, Bedfordshire, on a set of railway switches and crossings, which were being replaced as part of the Railway Upgrade Plan.

A pair of engineering trains were joined together connected by an umbilical and ran in parallel to simultaneously deliver tamping and dynamic track stabilisation (DTS) which simulated the equivalent of 200 trains passing over the tracks consecutively. Passenger trains were then able to start using the railway at speeds as high as 125mph as soon as the engineering team had finished because the track and ballast were firmly ‘bedded in’ – which meant Network Rail avoided thousands of pounds in compensation payments.

The news comes almost one year after Network Rail’s first successes with 125mph ‘high speed handbacks’ in January 2016 on regular plain line track. High speed handback ensures track is installed at each stage to its specific design tolerances, that care is taken while tamping to get the track to its final exact co-ordinates and that welding and stressing is completed as part of the core works.

Network Rail estimates that over US$6.2 million (£5 million) has already been saved by avoiding compensation payments since the start of the high speed handback programme.

For more information on companies in this article

Related Content

  • Queensland gets the message with ST Engineering
    August 29, 2024
    Train traveller information and passenger announcements enabled via Agil system
  • First full-scale Hyperloop test track ‘planned for 2016’
    March 2, 2015
    According to website The Verge, Hyperloop Transportation Technologies (HTT) has secured land for the first full-scale Hyperloop, planned for a 2016 launch in the California model town of Quay Valley. Building off Elon Musk's freely available designs, the crowdfunded company has marked out a five-mile stretch of Quay Valley adjacent to California's Interstate 5 freeway as a place where the innovative transportation system can be deployed. If successful, it would be the first full-size implementation of Musk'
  • Hayden AI cameras give Philadelphia freedom to bus riders
    March 4, 2025
    150 Septa buses and 20 trolley buses will monitor bus lane infringements
  • EU to fund pan-European EV infrastructure demo project
    April 17, 2012
    An innovative project to demonstrate what a pan-European infrastructure and service provision for electric vehicles could look like will receive almost €5 million (US$7.1 million) in EU co-funding from the TEN-T budget. The project, which was presented under the 2010 TEN-T Annual Call, constitutes an essential first step towards a possible viable deployment of open-access infrastructure for electric vehicles across the EU over the next ten years.