‘Formation flying’ engineering trains used to upgrade railway

In a bid to increase efficiencies and reduce delays for passengers, the UK’s Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete. The pioneering technique was used successfully at Sandy, Bedfordshire, on
February 16, 2017 Read time: 2 mins
In a bid to increase efficiencies and reduce delays for passengers, the UK’s 5021 Network Rail is trialling ‘formation flying’ engineering trains to repair and renew the 20,000 miles of railway track it is responsible for maintaining. It says this new approach to engineering could potentially save taxpayer-funded Network Rail US$313,000 (£250,000) per week in costs by allowing trains to run at higher speeds once engineering is complete.

The pioneering technique was used successfully at Sandy, Bedfordshire, on a set of railway switches and crossings, which were being replaced as part of the Railway Upgrade Plan.

A pair of engineering trains were joined together connected by an umbilical and ran in parallel to simultaneously deliver tamping and dynamic track stabilisation (DTS) which simulated the equivalent of 200 trains passing over the tracks consecutively. Passenger trains were then able to start using the railway at speeds as high as 125mph as soon as the engineering team had finished because the track and ballast were firmly ‘bedded in’ – which meant Network Rail avoided thousands of pounds in compensation payments.

The news comes almost one year after Network Rail’s first successes with 125mph ‘high speed handbacks’ in January 2016 on regular plain line track. High speed handback ensures track is installed at each stage to its specific design tolerances, that care is taken while tamping to get the track to its final exact co-ordinates and that welding and stressing is completed as part of the core works.

Network Rail estimates that over US$6.2 million (£5 million) has already been saved by avoiding compensation payments since the start of the high speed handback programme.

For more information on companies in this article

Related Content

  • Speeding ambulances through borders
    October 26, 2016
    David Crawford sees hope for stricken patients on the wrong side of the border. In treating patients with heart or stroke conditions, speed is of the essence.
  • Platform announcement: public transport is running 10 years behind schedule
    March 10, 2023
    Public transport worldwide is under pressure on a variety of fronts. Jon Salmon of Snapper Services UK explains why the industry should look more at data – and pick up some tips from the retail sector
  • Rail operator deploys Siemens technology for newly opened light rail line
    September 22, 2015
    TriMet's new MAX Orange Line, a light rail project between Portland and Milwaukie in the US incorporates Siemens’ advanced rail technologies, including its S70 light rail vehicles, rail signalling and communication systems and the company's first Sitras SES energy storage unit in the US that uses regenerative braking to sustainably power the line. The 12 kilometre line is the region's sixth construction project of the development project Metropolitan Area Express (MAX) to expand the city's transport net
  • Transport Secretary says high-speed rail and Northern Powerhouse ‘a priority’
    June 2, 2015
    In a keynote speech in Leeds, UK Transport Patrick McLoughlin has confirmed high-speed rail and Northern Powerhouse are a priority. He said that boosting growth in the north, rebalancing the economy and creating a Northern Powerhouse were a vital part of the long-term economic plan and confirmed that work on High Speed 2 (HS2) is on track to start in 2017. Work is also well underway on developing plans for high-speed east-west rail links. He confirmed that US$18 billion government funding would be inv