EBRD investment to modernise Serbia's railways

The European Bank for Reconstruction and Development (EBRD) is continuing to support the modernisation of Serbia’s transport infrastructure and promote further reform of the rail sector with a sovereign-guaranteed loan of up to €95 million (US$125 million) to the Serbian Railways company.
March 15, 2012 Read time: 2 mins
The 2001 European Bank for Reconstruction and Development (EBRD)  is continuing to support the modernisation of Serbia’s transport infrastructure and promote further reform of the rail sector with a sovereign-guaranteed loan of up to €95 million (US$125 million) to the 3911 Serbian Railways company.

The investment will finance the rehabilitation of key sections of Corridor X, the main north-south route running through Serbia, which is also the country’s key regional link with its neighbours.

As the most important component of the railway network in Serbia, Corridor X handles over 50 per cent of all rail traffic. However, much of it is in a poor state, resulting in speed restrictions, or is in need of modernisation to meet anticipated traffic flows. More than 50 per cent of the network operates at speeds of less than 60 km/hour.

The EBRD loan will help Serbian Railways to address these limitations by financing the modernisation of a 14km section of Corridor X from Belgrade Central Station through Rakovica to Resnik, as well as the renewal of approximately 50km of track along key sections of this Corridor. The project will enhance the speed and reliability of passenger and freight rail services in Serbia.

The EBRD is supporting the ongoing reform of Serbian Railways, particularly the creation of separate passenger, freight and infrastructure companies, and the opening of the rail freight market to private operators. The objective of these reforms is to increase efficiency, and the quality of rail services offered to the market.

For more information on companies in this article

Related Content

  • Developments in travel information display systems
    August 1, 2012
    David Crawford looks at recent developments in travel information display systems. It is important to remember that we are investing in Real-Time Passenger Information [RTPI] to increase ridership," says Robert Burke, Managing Director of New Zealand transit tracking technology specialist Connexionz, which has been involved in at-stop and remote passenger information since 1995. "Superior information improves the perception of public transport reliability and gives the passenger more choices and greater con
  • Turkmenistan railways modernise with Huawei GSM-R
    June 12, 2014
    Huawei is to supply its GSM-R solution for the Turkmenistan Buzhun-Serehtyaka and Bereket-Cilmammet integrated railway communications project. Huawei's customised solution features advanced communication technologies and equipment for the railway industry, including the DBS3800 distributed base stations and remote radio units (RRUs) which are installed at the top of towers, efficiently reducing the impact of antenna feeder loss on radio network coverage while satisfying the special local requirement that
  • Embedded connectivity delivers real time travel information
    February 3, 2012
    Ton Brand describes the GSM Association's Embedded mTelematics programme. As the world's roads become increasingly crowded, consumers and businesses are demanding better real-time information to help them both avoid traffic congestion and make smarter use of public transport. Embedding mobile connectivity directly into vehicles can enable drivers and passengers to see live traffic flows in their localities, as well as the expected arrival time of the next bus, ferry or tram
  • Toll plaza conversion will reduce congestion on I-95
    April 17, 2012
    In an effort to reduce congestion in a busy corridor for motorists and commercial freight carriers, Delaware Department of Transportation (DelDOT) appointed TransCore as the lead integrator on a project to convert the Newark Toll Plaza on I-95, adding two new electronic highway speed lanes on both the north and south bound plazas. Plaza throughput is now about to jump from 250-300 transactions per lane per hour to an estimated 2,000. The US$32 million “shovel ready” project was fully funded through the Amer