Brazil-Spain group could lose highway contract

An engineering consortium made up of Brazil's Mendes Junior and Spain's Isolux Corsán could be stripped of its US$208 million contract to build part of the northern stretch of the Mario Covas beltway surrounding the city of São Paulo. The consortium, led by Mendes Junior, is having difficulty honouring commitments due to a lack of cash flow and, according to São Paulo state highway company Dersa, it is not completing works according to the contract schedule signed in January 2013, local paper Folha de Sã
April 10, 2015 Read time: 2 mins
RSSA consortium of Brazil's 6871 Mendes Junior and Spain's 1954 Isolux Corsán could lose its US$208 million contract to build part of the northern section of the Mario Covas beltway around the Brazilian city of São Paulo.

The consortium, led by Mendes Junior, is falling behind schedule because of cash flow problems, according to São Paulo state highway company 5947 Dersa. The deal was signed in January 2013, local paper Folha de São Paulo reported.

If matters do not improve this month, "it is very likely that we will terminate our agreement based on a breach of contract," Dersa president Laurence Casagrande was quoted as saying.

The 180km Rodoanel Mário Covas beltway is partially with a radius of around 23km from the geographical centre of Sao Paulo. It was named after Mário Covas, mayor of the city between 1983–1985 and a state governor from 1994-2001 until his death from cancer. It is a controlled access highway with a speed limit of 100kph.

The northern segment is the last of the bletway’s four sections to be built. Construction of Dersa’s stretch of the northern section was originally scheduled to be completed last year but was rescheduled to January 2016. However, at the beginning of this year, Dersa pushed back the completion date to the first half of 2017.

If terminated, Dersa could transfer the work to local construction company 4740 Odebrecht, which submitted the next best offer for the contract. If not, a new tender for the remaining work could be launched, according to the news report.

Mendes Junior is one of many engineering companies under investigated by the federal government's so called car wash corruption probe.

For more information on companies in this article

Related Content

  • UK defaults to hard shoulder running to expand motorway capacity
    April 8, 2014
    Hard shoulder running has become the UK’s default response to increasing motorway capacity as Colin Sowman reports. Facing a predicted 46% increase in traffic levels by 2040 and the current economic recovery leading to more people travelling to, from and for work leaves the UK government under short- and long-term pressure to increase the capacity on the main motorway network. Particular sections of motorways are already experiencing repeated, sometimes tidal, congestion and both tight Treasury limits and t
  • Johnson Controls targets US with battery plant for start-stop vehicle technology
    April 23, 2012
    Johnson Controls has announced plans to invest US$138.5 million to convert its battery plant near Toledo, Ohio, in the US, into an Absorbent Glass Mat (AGM) battery facility for Start-Stop and other high efficiency vehicles. Subject to final state and local incentives, the facility will be the company's first such plant in the United States.
  • How C/AVs could serve rural communities
    July 23, 2019
    In Ireland, there is low population density and a lot of rain – which can make last-mile journeys a trial. Orla O’Halloran at Arup has some thoughts on how C/AVs could serve rural communities Connected and autonomous vehicles (C/AVs) have the potential to be a vital link for people in rural communities, as part of a wider Mobility as a Service (MaaS) solution. That is the view of Orla O’Halloran, intelligent mobility consultant at Arup. She believes that MaaS needs to be considered in conjunction with ot
  • Fugro Roadware wins data collection contract
    April 17, 2012
    Fugro Roadware has won a two-year, US$3 million, contract from the US SHRP 2 (Strategic Highway Research Programme 2), for the collection of roadway data at highway speed, using ARAN’s (Automatic Road Analysers) on selected roads, within the six SHRP 2 naturalistic driving study sites.