Brazil-Spain group could lose highway contract

An engineering consortium made up of Brazil's Mendes Junior and Spain's Isolux Corsán could be stripped of its US$208 million contract to build part of the northern stretch of the Mario Covas beltway surrounding the city of São Paulo. The consortium, led by Mendes Junior, is having difficulty honouring commitments due to a lack of cash flow and, according to São Paulo state highway company Dersa, it is not completing works according to the contract schedule signed in January 2013, local paper Folha de Sã
April 10, 2015 Read time: 2 mins
RSSA consortium of Brazil's 6871 Mendes Junior and Spain's 1954 Isolux Corsán could lose its US$208 million contract to build part of the northern section of the Mario Covas beltway around the Brazilian city of São Paulo.

The consortium, led by Mendes Junior, is falling behind schedule because of cash flow problems, according to São Paulo state highway company 5947 Dersa. The deal was signed in January 2013, local paper Folha de São Paulo reported.

If matters do not improve this month, "it is very likely that we will terminate our agreement based on a breach of contract," Dersa president Laurence Casagrande was quoted as saying.

The 180km Rodoanel Mário Covas beltway is partially with a radius of around 23km from the geographical centre of Sao Paulo. It was named after Mário Covas, mayor of the city between 1983–1985 and a state governor from 1994-2001 until his death from cancer. It is a controlled access highway with a speed limit of 100kph.

The northern segment is the last of the bletway’s four sections to be built. Construction of Dersa’s stretch of the northern section was originally scheduled to be completed last year but was rescheduled to January 2016. However, at the beginning of this year, Dersa pushed back the completion date to the first half of 2017.

If terminated, Dersa could transfer the work to local construction company 4740 Odebrecht, which submitted the next best offer for the contract. If not, a new tender for the remaining work could be launched, according to the news report.

Mendes Junior is one of many engineering companies under investigated by the federal government's so called car wash corruption probe.

For more information on companies in this article

Related Content

  • Efkon Group wins major contract in South Africa
    February 6, 2012
    Efkon Group’s subsidiary in South Africa, Tollink, has been awarded a major contract to install and operate an intelligent transportation system on freeways in South Africa.
  • Hungary’s $159m AV test track gears up
    June 1, 2020
    Construction of the Zalazone project started in 2017 and is on schedule
  • Motorists want roads repaired before smart motorways, says survey
    December 5, 2014
    According to research by Bury-based online car supermarket JamJar Direct, which indicates that 47 per cent of Greater Manchester motorists claim to have been affected by the construction works, communications around the M60 smart motorway improvements are sorely lacking. Almost two thirds of Greater Manchester motorists (62 per cent) are aware that the M60 is being turned into a smart motorway, but over 40 per cent, equivalent to 81,000 vehicles per day using affected stretch of M60 between junctions 8 a
  • Florida cities expand red light cameras
    January 23, 2013
    West Palm Beach is to significantly expand its red-light camera program in 2013 after commissioners approved plans to install cameras at twenty-five new intersections, bringing the number of intersections equipped to catch drivers who illegally run red lights to thirty-two. The move comes despite a recent city police report that tracked five of the existing seven red-light cameras and found crashes nearly doubled in those locations between February 2011 and January 2013, to 66 from 36. Police Chief Vince De