Brazil-Spain group could lose highway contract

An engineering consortium made up of Brazil's Mendes Junior and Spain's Isolux Corsán could be stripped of its US$208 million contract to build part of the northern stretch of the Mario Covas beltway surrounding the city of São Paulo. The consortium, led by Mendes Junior, is having difficulty honouring commitments due to a lack of cash flow and, according to São Paulo state highway company Dersa, it is not completing works according to the contract schedule signed in January 2013, local paper Folha de Sã
April 10, 2015 Read time: 2 mins
RSSA consortium of Brazil's 6871 Mendes Junior and Spain's 1954 Isolux Corsán could lose its US$208 million contract to build part of the northern section of the Mario Covas beltway around the Brazilian city of São Paulo.

The consortium, led by Mendes Junior, is falling behind schedule because of cash flow problems, according to São Paulo state highway company 5947 Dersa. The deal was signed in January 2013, local paper Folha de São Paulo reported.

If matters do not improve this month, "it is very likely that we will terminate our agreement based on a breach of contract," Dersa president Laurence Casagrande was quoted as saying.

The 180km Rodoanel Mário Covas beltway is partially with a radius of around 23km from the geographical centre of Sao Paulo. It was named after Mário Covas, mayor of the city between 1983–1985 and a state governor from 1994-2001 until his death from cancer. It is a controlled access highway with a speed limit of 100kph.

The northern segment is the last of the bletway’s four sections to be built. Construction of Dersa’s stretch of the northern section was originally scheduled to be completed last year but was rescheduled to January 2016. However, at the beginning of this year, Dersa pushed back the completion date to the first half of 2017.

If terminated, Dersa could transfer the work to local construction company 4740 Odebrecht, which submitted the next best offer for the contract. If not, a new tender for the remaining work could be launched, according to the news report.

Mendes Junior is one of many engineering companies under investigated by the federal government's so called car wash corruption probe.

For more information on companies in this article

Related Content

  • Deaths up and road safety spending down in England
    July 12, 2012
    Fifty local councils in England saw more than a ten per cent increase in killed and seriously injured (KSI) crash rates between 2010 and 2011, according to an Institute for Advanced Motorists (IAM) analysis of the new road accident figures. The biggest increases in KSI numbers were in St Helens – 62 per cent, Portsmouth – 57 per cent, Stoke on Trent – 57 per cent, and Coventry – 51 per cent. A further 76 councils saw increases in the KSI rate above the national average of two per cent.
  • Kapsch sets course for higher profitability
    February 26, 2015
    Kapsch TrafficCom experienced stable business development in the first three quarters of 2014/2015 with existing installation and operation projects. The Group was also able to obtain a number of new orders in Australia during the third quarter, although new major orders, upon which the innovation and growth plans are based, remained elusive due to the lack of corresponding invitations to tender. Revenue of the Group during the first three quarters of the 2014/15 fiscal year was US$283.5 million, slightly b
  • Live demonstrations at 2010 ITS annual meeting
    August 2, 2012
    The practical, day-to-day co-working which goes on at Houston TranStar will form a major part of the demonstrations at the 2010 Annual Meeting, says co-chair of the organising committee Metropolitan Transit Authority of Harris County Chief of Police Thomas C. Lambert.
  • LB Foster wins $60 million Honolulu rail contract
    July 27, 2012
    Pennsylvania-based LB Foster Company has been awarded the company’s largest rail products contract, valued at approximately US$60 million, by contractor Kiewit/Kobayashi, a joint venture for the county-wide construction of the Honolulu Authority for Rapid Transportation (HART) passenger transit system. LB Foster rail, concrete ties, direct fixation fasteners, third rail with accessories and special trackwork will be installed throughout the Honolulu Rail Transit project’s new elevated railway system and mai