Brazil-Spain group could lose highway contract

An engineering consortium made up of Brazil's Mendes Junior and Spain's Isolux Corsán could be stripped of its US$208 million contract to build part of the northern stretch of the Mario Covas beltway surrounding the city of São Paulo. The consortium, led by Mendes Junior, is having difficulty honouring commitments due to a lack of cash flow and, according to São Paulo state highway company Dersa, it is not completing works according to the contract schedule signed in January 2013, local paper Folha de Sã
April 10, 2015 Read time: 2 mins
RSSA consortium of Brazil's 6871 Mendes Junior and Spain's 1954 Isolux Corsán could lose its US$208 million contract to build part of the northern section of the Mario Covas beltway around the Brazilian city of São Paulo.

The consortium, led by Mendes Junior, is falling behind schedule because of cash flow problems, according to São Paulo state highway company 5947 Dersa. The deal was signed in January 2013, local paper Folha de São Paulo reported.

If matters do not improve this month, "it is very likely that we will terminate our agreement based on a breach of contract," Dersa president Laurence Casagrande was quoted as saying.

The 180km Rodoanel Mário Covas beltway is partially with a radius of around 23km from the geographical centre of Sao Paulo. It was named after Mário Covas, mayor of the city between 1983–1985 and a state governor from 1994-2001 until his death from cancer. It is a controlled access highway with a speed limit of 100kph.

The northern segment is the last of the bletway’s four sections to be built. Construction of Dersa’s stretch of the northern section was originally scheduled to be completed last year but was rescheduled to January 2016. However, at the beginning of this year, Dersa pushed back the completion date to the first half of 2017.

If terminated, Dersa could transfer the work to local construction company 4740 Odebrecht, which submitted the next best offer for the contract. If not, a new tender for the remaining work could be launched, according to the news report.

Mendes Junior is one of many engineering companies under investigated by the federal government's so called car wash corruption probe.

For more information on companies in this article

Related Content

  • Salvador metro engineering contract awarded to Egis
    January 9, 2014
    French engineering and construction firm Egis has been awarded a US$16 million engineering contract by Brazil’s build and operate concessionaire CCR (Companhia de Concessões Rodoviárias) for the construction of the Salvador metro in the state capital of Bahia, Brazil. The project comprises the completion of the seven kilometre line 1, which is partly underground, the construction of five kilometres of extensions to this first line and the construction of the 24 kilometre line 2, serving Salvador’s inter
  • A carbon free and accident free Europe by 2015?
    February 2, 2012
    By 2050, the Europe Commission aims to make transport in Europe carbon- and accident-free. Between now and then, however, a significant technological development and deployment effort is needed. Here, Neelie Kroes, European Commission Vice-President for the Digital Agenda, talks about what's being done. In many respects, COOPERS, CVIS and SAFESPOT, set up by the European Commission (EC) to explore the potential of cooperative infrastructure systems, are already legacy projects. Between them, the three devel
  • MoDOT launches ‘Road to Tomorrow’
    June 22, 2015
    The Missouri Highways and Transportation Commission (MHTC) has launched plans to utilise innovation and construction rebuild the state’s oldest interstate highway, Interstate 90. It is to make the highway from Kansas City to St Louis available to private industry, entrepreneurs and innovators as a laboratory for construction of the next generation of highways. Missouri Department of Transportation (MoDOT) chief engineer Ed Hassinger has appointed a team of MoDOT experts to solicit and evaluate ideas fro
  • Michigan DoT implements truck parking initiative
    September 9, 2014
    A new project is balancing up the needs of truckers wanting a break from the road and the availability of parking spots in Michigan. Commercial truck drivers typically require around 30 minutes to find somewhere to stop for a rest. They frequently find that the five public rest areas on the heavily-trafficked 129-mile stretch of I-94 in southwest Michigan, which carries around 10,000 trucks a day in the Canada-Detroit-Chicago corridor, are full.