Skip to main content

Balfour Beatty JV to deliver UK smart motorways package

The Balfour Beatty Vinci joint venture has been awarded a contract by Highways England to deliver a smart motorway package worth up to US$792 million, the largest of Highways England’s three packages within its US$2.3 billion Smart Motorway Programme. The joint venture will deliver smart motorway upgrades to a ten mile stretch of the M5 Junctions 4a to 6 in Worcestershire; a 12 mile section of the M6 Junctions 2 to 4 in the Midlands and a 32 mile stretch of the M4 Junctions 3 to 12 in London and Berkshir
July 22, 2015 Read time: 2 mins
The 3902 Balfour Beatty 5176 Vinci joint venture has been awarded a contract by 8101 Highways England to deliver a smart motorway package worth up to US$792 million, the largest of Highways England’s three packages within its US$2.3 billion Smart Motorway Programme.

The joint venture will deliver smart motorway upgrades to a ten mile stretch of the M5 Junctions 4a to 6 in Worcestershire; a 12 mile section of the M6 Junctions 2 to 4 in the Midlands and a 32 mile stretch of the M4 Junctions 3 to 12 in London and Berkshire.

These upgrades are aimed at increasing capacity, reducing congestion and shortening journey times for the thousands of road users who use these parts of the network every day. Extra capacity will be added to the motorways through the conversion of the hard shoulder to a permanent running lane. Electronic signs, operated by a regional control centre, will be installed to manage the flow of traffic in response to driving conditions.

Work on the M5 upgrade is due to start in the autumn of this year. Subject to statutory approval and continued value for money, the M6 is expected to start work in 2017/18 and the M4 scheme in 2016/17. Final target costs for these contracts will be agreed with Highways England.

For more information on companies in this article

Related Content

  • Highways England pilots project to reduce congestion along M62
    November 13, 2017
    Highways England (HE) has begun piloting a £7 million ($9 million) project to reduce congestion at the Croft Interchange – where junction 21a of the M6 meets junction 10 of the M62, near Warrington, Cheshire. The project aims to provide drivers with smoother and more reliable journey times.
  • Government green lights road and rail improvements
    July 19, 2013
    UK Transport Secretary Patrick McLoughlin has confirmed a £1.2 billion order for more state of-the art trains to transform rail travel on one of Britain’s busiest intercity routes. The 270 carriages will be manufactured in Britain by Hitachi Rail Europe as part of the government’s overall £5.8 billion Intercity Express Programme (IEP). The trains will operate on the East Coast Main Line from 2019 and will deliver significant benefits to passengers, including boosting capacity by 18 per cent, improving trai
  • Major road projects to improve journeys in Merseyside and Cheshire
    September 1, 2017
    Two major new road schemes worth more than US$388 million (£300 million) are set to cut congestion and improve journey times for hundreds of thousands of drivers in Merseyside and Cheshire, UK. Highways England has set out its preferred options for upgrading the key route to the Port of Liverpool and creating a new junction on the M56 near Runcorn following public consultations earlier this year.
  • The UK’s busiest crossing adopts free flow charging
    April 30, 2015
    Colin Sowman looks at the transition to free-flow charging on the Dartford Crossing, a notorious congestion blackspot on the UK motorway network. The Dartford Crossing, where London’s orbital M25 motorway crosses the lower reaches of the River Thames 32km (20 miles) to the east of Central London, has long been a major source of congestion. Now, to alleviate the congestion caused by some 50 million crossings per year, the Highways Agency has adopted a free-flow charging system - but the Crossing’s location a