Skip to main content

Colombian highway sees ITS tested to the extreme

One of the most challenging road construction and ITS projects currently underway is the upgrading of the road from Bogota to Villavicencio. Currently it takes four hours to make the 86km journey between Bogota and Villavicencio using the existing single lane in each direction road which passes through some very challenging terrain. It is the only ground connection between central Colombia and the eastern region which represents 40% of the country’s territory.
November 13, 2014 Read time: 4 mins
A bride being constructed over the Quebrada Blanca will carry the road between tunnels 10 and 11 in section three of the new highway

One of the most challenging road construction and ITS projects currently underway is the upgrading of the road from Bogota to Villavicencio.

Currently it takes four hours to make the 86km journey between Bogota and Villavicencio using the existing single lane in each direction road which passes through some very challenging terrain. It is the only ground connection between central Colombia and the eastern region which represents 40% of the country’s territory. The road is the only economical way to join the eastern region of the country with Bogota, Colombia’s capital, and consequently it has the highest traffic growth in the country.

An upgrade to a segregated highway with two lanes in each direction has been planned by the National Roads Institute INVÍAS. However, the new road will have to run through 18 tunnels totalling almost 15km in length as well as across 50 bridges and viaducts with a total length of 5,228m. In some section the work is an upgrade to the existing roadway but most, including most the tunnels and bridges, is completely new green-field infrastructure.

Colombian concessionaire 7764 Coviandes Andes will manage the road and has awarded Spanish consultancy and technology firm 509 Indra a US$34m contract to design and install traffic management technology in 18 tunnels, 41 bridges and three overpasses along a particularly challenging 45km section. It is expected that more than 1,200 vehicles carrying hazardous goods (usually fuel) will use this stretch of the road each day, so the new tunnels are designed to the European EuroTAPstandards for maximum safety and efficiency. While three existing tunnels will be utilised the remaining tunnels and bridges are under construction or have been completed.

The contract also includes a new control centre at Naranjal which will house five operators and will be integrated with those at Boquerón and Buenavista to manage the traffic in the whole infrastructure. As with the existing control centres, the new one will be fitted with Indra’s Horus integrated roadway and tunnel management system which provides the operators with real-time information.

Monitoring and control systems in the tunnels are centred on 215 fixed CCTV/ machine vision cameras which detect incidents, stationary vehicles or obstacles, wrong way drivers and pedestrians. There are also individual detectors for visibility, fire and carbon monoxide. SOS posts along with communications including loudspeakers and road signage are available should an incident occur. All the tunnels will also be equipped with power generators and backup power, a lighting system and emergency evacuation routes.

Coviandes has also specified automatic incident detection systems along the full 86km between Bogota and Villavicencio including 72 pan and tilt cameras and a fourth weather station added to the three that are already deployed. There will be also variable message signs along the roadway to provide drivers with real-time information about road conditions, speed limits and incidents.

In normal operation Boquerón will remain the lead control room with the other two acting as monitors. However, all three control centres can share the control of the road and each is equipped to manage the entire road and take the lead in the event of an incident. This includes a complex radio communication system based on the transmission of the digital mobile radio signals from three mountains joined by a radio link that covers the entire length of the road.

In the event of an incident both single lane running and contraflow arrangements can be quickly implemented using either the VMS or a combination of VMS and cones. The design of the new road is such that in some sections it runs parallel to the existing road so there will be seven sections where traffic can be diverted onto and off of the old road in the event of a major incident. 

While the first section will be opened this December, it will be until July 2017 before the highway is finished and once completed it will cut the journey to about 90 minutes and reduce vehicle operating costs by up to 60%. 

Related Content

  • October 2, 2014
    Mexico implements Indra traffic management technology
    Indra, in partnership with Auneti (Autopista Necaxa-Tihuatlán) and FCC, has deployed traffic management technology in the six tunnels of the new Necaxa-Tihuatlán highway in Mexico. The US$18 million project also includes intelligent transportation systems (ITS) and control and communication systems on the 83 kilometres of highway sections 1 and 2. A new operational control centre equipped with Indra's Horus integrated roadway and tunnel management solution manages traffic along the new road's two sectio
  • September 14, 2016
    Mexico’s Durango-Mazatlan highway sets tunnel safety standard
    Mauro Nogarin looks at the management of the longer tunnels on Mexico’s Durango-Mazatlan highway. In recent years the National Infrastructure Fund of Mexico has increased investment in the installation of ITS systems on selected highways to increase road safety. One such major investment is the 230km long Durango-Mazatlan highway which is 12m in width and has an average speed of 110km/h.
  • August 26, 2016
    Mexico’s Durango-Mazatlan highway sets tunnel safety standard
    Mauro Nogarin looks at the management of the longer tunnels on Mexico’s Durango-Mazatlan highway. In recent years the National Infrastructure Fund of Mexico has increased investment in the installation of ITS systems on selected highways to increase road safety. One such major investment is the 230km long Durango-Mazatlan highway which is 12m in width and has an average speed of 110km/h.
  • November 27, 2017
    Indra tunnel solution used on four tunnels for Bogotá-Villavicencio divided highway project
    Indra, Coviandes's principal technology partner on the Bogotá-Villavicencio divided highway project, has implemented its traffic and tunnel solution on four tunnels located between Cáqueza and Puente Quetame, in Columbia. It is designed with the intention of facilitating operation, automating processes, reducing the risk of incidents, streamlining management and providing safety for drivers. Called Horus, the solution will be installed on the Herradura, Moscosio, Culebra and Oro Perdido tunnels. It