Signal optimisation reduces congestion, improves travel times

The Metropolitan Government of Nashville and Davidson County's Department of Public Works(MPW) identified seven corridors in the County that experience heavy traffic congestion and needed traffic signal timing improvements to improve traffic flow as well as air quality and fuel consumption. The seven corridors included a total of 223 signalised intersections. To conduct this study, termed the Traffic Signal Optimisation Study for the Metro Nashville Signal System, MPW received funding from the Federal Conge
February 2, 2012 Read time: 4 mins
RSSThe 2141 Metropolitan Government of Nashville and Davidson County's Department of Public Works(MPW) identified seven corridors in the County that experience heavy traffic congestion and needed traffic signal timing improvements to improve traffic flow as well as air quality and fuel consumption. The seven corridors included a total of 223 signalised intersections. To conduct this study, termed the Traffic Signal Optimisation Study for the Metro Nashville Signal System, MPW received funding from the Federal Congestion Mitigation and Air Quality (CMAQ) Program via the 2142 Nashville Area Metropolitan Planning Organisation (MPO).

The consultant team MPW selected to conduct this study was 422 Kimley-Horn and Associates, with Stammer Transportation Engineering, and Bowlby & Associates as part of the team. The project scope included significant data collection efforts, an assessment of existing Project:
• Traffic signal optimisation, Metro Nashville, Tennessee, US

Cost:
• $750,000 (Phase I)
ROI:
• $14,770,900 first year (21:1)
•$46,326,550 over three years (62:1)

Benefits:
•Reduction in traffic congestion for Davidson County motorists
• Environmental improvements - reduction in fuel consumption
conditions, identification of potential improvements, the development of timing plans for each period of the day including weekdays and weekend, and field implementation of the proposed timing plans. In addition, the project included the development of MPW's Traffic Signal Timing and Phasing Policy, development and presentation of a two-part training programme for MPW staff, travel time and delay studies, air quality analyses and complete project documentation.

Benefits

Results from the signal timing effort included a 20 per cent reduction in delay for the seven corridors, with the greatest delay reduction of approximately 37 per cent along the Nolensville Pike and Harding Place corridors. Benefits in reduced fuel consumption also were realised with this project. A reduction of nearly six per cent in fuel consumption along the seven corridors was achieved. Furthermore, improvements in air quality were achieved. Volatile organic compounds were reduced by 3 per cent, nitrogen oxides by approximately 1 per cent, and carbon monoxide by nearly 1 per cent.

Economic analysis

Based on the results from the delay study, fuel consumption analysis, and the air quality analysis, an economic evaluation was conducted for the project to determine what benefits arose from the implementation of the new signal timing plans. The benefits studied included reduced road user costs from reduced delay experienced by the motoring public, air pollutants and fuel consumption. To determine these economic benefits, Kimley-Horn studied the AM, midday, and PM peak periods of the weekdays. Therefore, economic benefits were not quantified for the non-peak hours of the day and are not reflected in this analysis.

To calculate the cost savings resulting in the reduction of delay by the motoring public, a dollar value was assigned to the delay. The 324 US Department of Transportation provides data for this purpose. Using this data, analyses were made for each corridor in the project, and these results were tallied to yield a benefit in terms of reduced delay for the entire project. For a one-year period this benefit was calculated to be $14,770,900.

Economic benefits also were realised for the reduced emissions that resulted from the improved signal timing plans. This was calculated by assigning a cost to each of Economic analysis the three pollutants, as documented by the Federal Highways Administration. For the entire project over a one year period the benefit was found to be $33,655.

Similarly, the economic benefit was determined for the reduced fuel consumption. A conservative value of $2.00 per gallon of fuel was used for this analysis. For the whole project, this was found to be $637,630 for a one-year timeframe.

By using an engineering fee for this project, a benefit-to cost ratio was calculated. The benefits were the sum of the delay, emissions and fuel benefits over a one-year timeframe totaling $15,442,180. The cost was the contract value for the project: $750,000. This yielded a one year benefit-to-cost ratio of 21:1. However, the implemented signal timing plans will be used and prove to be beneficial for a time period longer than one year.

Typically the useful life for signal timing plans is three years, as recommended by the ITE ("At a minimum, an operating agency should budget to retime traffic signals at least every three years.") Therefore, the three-year benefit is $46,326,550, while the cost remains only $750,000. This yields a three-year benefit-to-cost ratio of 62:1.


RSS

Related Content

  • Cost saving multi-agency transportation and emergency management
    May 3, 2012
    Although the recession had dramatically reduced traffic volumes in the past few years, the economy was on the brink of a recovery that portended well for jobs but poorly for traffic congestion. Leaders of four government agencies in Houston, Texas, got together to discuss how to collectively cope with the expected increase in vehicles on the road. "They knew they couldn't pour enough concrete to solve the problem, and they also knew the old model of working in a vacuum as standalone entities would fail," sa
  • Reducing incident clear up times, saving money
    January 24, 2012
    In 2007 in Atlanta, Georgia, it took over four hours to open the road after a major commercial vehicle incident. Not any more. Four years ago the Texas Transportation Institute (TTI) cited Atlanta, Georgia as the third-most congested city in the United States. Each traveller in metro Atlanta lost an incredible 57 hours a year to traffic delays, wasting 40 gallons of fuel while sitting in traffic. In 2007, it took nearly four and a half hours to open travel lanes after an average tractor-trailer incident. Th
  • Mounting benefits of dynamic tolling project
    January 30, 2012
    Wisconsin's four-year HOT lanes pilot project, launched in May 2008, cost US$18.8 million to construct. Halfway into the project, which uses variably priced, or dynamic, tolling to improve highway efficiency, the benefits are mounting. The problem was obvious, and frustrating, to anyone who ever sat in bumper-to-bumper traffic on State Route 167 and watched a lone car whiz by every 20 seconds or so in the carpool lane. But for planners at the Washington State Department of Transportation, the conundrum was
  • Eco fuel economy
    April 19, 2012
    A study conducted by VTT Technical Research Centre of Finland suggests that there is practically no difference between commercial petrol grades 95E10 and 98E5 sold in Finland with regard to fuel consumption during normal driving. The finding is based on driving tests conducted by VTT using six used cars of different make under laboratory conditions. It has been claimed in public that fuel consumption is higher with 95E10 petrol than with its predecessor 95E or the 98E5 petrol currently on the market. The su