The Metropolitan Government of Nashville and Davidson County's Department of Public Works(MPW) identified seven corridors in the County that experience heavy traffic congestion and needed traffic signal timing improvements to improve traffic flow as well as air quality and fuel consumption. The seven corridors included a total of 223 signalised intersections. To conduct this study, termed the Traffic Signal Optimisation Study for the Metro Nashville Signal System, MPW received funding from the Federal Conge
February 2, 2012 Read time: 4 mins
RSSThe 2141 Metropolitan Government of Nashville and Davidson County's Department of Public Works(MPW) identified seven corridors in the County that experience heavy traffic congestion and needed traffic signal timing improvements to improve traffic flow as well as air quality and fuel consumption. The seven corridors included a total of 223 signalised intersections. To conduct this study, termed the Traffic Signal Optimisation Study for the Metro Nashville Signal System, MPW received funding from the Federal Congestion Mitigation and Air Quality (CMAQ) Program via the 2142 Nashville Area Metropolitan Planning Organisation (MPO).

The consultant team MPW selected to conduct this study was 422 Kimley-Horn and Associates, with Stammer Transportation Engineering, and Bowlby & Associates as part of the team. The project scope included significant data collection efforts, an assessment of existing Project:
• Traffic signal optimisation, Metro Nashville, Tennessee, US

Cost:
• $750,000 (Phase I)
ROI:
• $14,770,900 first year (21:1)
•$46,326,550 over three years (62:1)

Benefits:
•Reduction in traffic congestion for Davidson County motorists
• Environmental improvements - reduction in fuel consumption
conditions, identification of potential improvements, the development of timing plans for each period of the day including weekdays and weekend, and field implementation of the proposed timing plans. In addition, the project included the development of MPW's Traffic Signal Timing and Phasing Policy, development and presentation of a two-part training programme for MPW staff, travel time and delay studies, air quality analyses and complete project documentation.

Benefits

Results from the signal timing effort included a 20 per cent reduction in delay for the seven corridors, with the greatest delay reduction of approximately 37 per cent along the Nolensville Pike and Harding Place corridors. Benefits in reduced fuel consumption also were realised with this project. A reduction of nearly six per cent in fuel consumption along the seven corridors was achieved. Furthermore, improvements in air quality were achieved. Volatile organic compounds were reduced by 3 per cent, nitrogen oxides by approximately 1 per cent, and carbon monoxide by nearly 1 per cent.

Economic analysis

Based on the results from the delay study, fuel consumption analysis, and the air quality analysis, an economic evaluation was conducted for the project to determine what benefits arose from the implementation of the new signal timing plans. The benefits studied included reduced road user costs from reduced delay experienced by the motoring public, air pollutants and fuel consumption. To determine these economic benefits, Kimley-Horn studied the AM, midday, and PM peak periods of the weekdays. Therefore, economic benefits were not quantified for the non-peak hours of the day and are not reflected in this analysis.

To calculate the cost savings resulting in the reduction of delay by the motoring public, a dollar value was assigned to the delay. The 324 US Department of Transportation provides data for this purpose. Using this data, analyses were made for each corridor in the project, and these results were tallied to yield a benefit in terms of reduced delay for the entire project. For a one-year period this benefit was calculated to be $14,770,900.

Economic benefits also were realised for the reduced emissions that resulted from the improved signal timing plans. This was calculated by assigning a cost to each of Economic analysis the three pollutants, as documented by the Federal Highways Administration. For the entire project over a one year period the benefit was found to be $33,655.

Similarly, the economic benefit was determined for the reduced fuel consumption. A conservative value of $2.00 per gallon of fuel was used for this analysis. For the whole project, this was found to be $637,630 for a one-year timeframe.

By using an engineering fee for this project, a benefit-to cost ratio was calculated. The benefits were the sum of the delay, emissions and fuel benefits over a one-year timeframe totaling $15,442,180. The cost was the contract value for the project: $750,000. This yielded a one year benefit-to-cost ratio of 21:1. However, the implemented signal timing plans will be used and prove to be beneficial for a time period longer than one year.

Typically the useful life for signal timing plans is three years, as recommended by the ITE ("At a minimum, an operating agency should budget to retime traffic signals at least every three years.") Therefore, the three-year benefit is $46,326,550, while the cost remains only $750,000. This yields a three-year benefit-to-cost ratio of 62:1.


RSS

Related Content

  • Travel data critical to traffic management, traveller information
    January 31, 2012
    The ability to bundle together travel data from several discrete sources and fuse it to give a more comprehensive overview of events to stakeholders is the key aim of Viajeo, which is conducting trials in several cities around the world. Here, Ertico's Yanying Li writes about the project in more detail
  • Cost benefit: just $25 boosts pedestrian safety in Florida
    April 29, 2019
    A relatively straightforward change to the way that pedestrians cross the street in a Florida city has made a significant safety improvement. And what’s more, it was cheap, finds David Crawford Installing a lead pedestrian interval (LPI) system at 25 central business district signalised intersections in the Florida city of Lakeland has cut numbers of incidents involving pedestrians by some 60% - at a cost of US$25 for 30 minutes' work, according to traffic operations manager Angelo Rao.
  • Road space utilisation improves travel times, reduces costs
    February 1, 2012
    For major road works schemes, necessary lane closures are timed to minimise congestion, most frequently at night and on weekends when traffic is at its lightest. As a result, rigid timetables are used in planning, programming and implementing work. In the UK, to calculate the expected traffic demand through roads works, historic profiles from the loop-based MIDAS (Motorway Incident Detection Automatic Signalling) system were used. These provided a valuable indicator of anticipated traffic behaviour but were
  • InfoConnect delivers accurate travel information on all levels
    August 1, 2012
    Deryk Whyte provides an overview of how the New Zealand Transport Agency's InfoConnect concept was developed. Historically, the New Zealand Transport Agency (NZTA) (formerly Transit New Zealand) has faced challenges in communicating effectively with road users, its customers, about highway-related events or incidents in a timely, accurate manner. Prior to 2007, Transit relied on a third-party organisation to collect and disseminate national road condition information. This often resulted in incomplete infor