Signal optimisation reduces congestion, improves travel times

The Metropolitan Government of Nashville and Davidson County's Department of Public Works(MPW) identified seven corridors in the County that experience heavy traffic congestion and needed traffic signal timing improvements to improve traffic flow as well as air quality and fuel consumption. The seven corridors included a total of 223 signalised intersections. To conduct this study, termed the Traffic Signal Optimisation Study for the Metro Nashville Signal System, MPW received funding from the Federal Conge
February 2, 2012 Read time: 4 mins
RSSThe 2141 Metropolitan Government of Nashville and Davidson County's Department of Public Works(MPW) identified seven corridors in the County that experience heavy traffic congestion and needed traffic signal timing improvements to improve traffic flow as well as air quality and fuel consumption. The seven corridors included a total of 223 signalised intersections. To conduct this study, termed the Traffic Signal Optimisation Study for the Metro Nashville Signal System, MPW received funding from the Federal Congestion Mitigation and Air Quality (CMAQ) Program via the 2142 Nashville Area Metropolitan Planning Organisation (MPO).

The consultant team MPW selected to conduct this study was 422 Kimley-Horn and Associates, with Stammer Transportation Engineering, and Bowlby & Associates as part of the team. The project scope included significant data collection efforts, an assessment of existing Project:
• Traffic signal optimisation, Metro Nashville, Tennessee, US

Cost:
• $750,000 (Phase I)
ROI:
• $14,770,900 first year (21:1)
•$46,326,550 over three years (62:1)

Benefits:
•Reduction in traffic congestion for Davidson County motorists
• Environmental improvements - reduction in fuel consumption
conditions, identification of potential improvements, the development of timing plans for each period of the day including weekdays and weekend, and field implementation of the proposed timing plans. In addition, the project included the development of MPW's Traffic Signal Timing and Phasing Policy, development and presentation of a two-part training programme for MPW staff, travel time and delay studies, air quality analyses and complete project documentation.

Benefits

Results from the signal timing effort included a 20 per cent reduction in delay for the seven corridors, with the greatest delay reduction of approximately 37 per cent along the Nolensville Pike and Harding Place corridors. Benefits in reduced fuel consumption also were realised with this project. A reduction of nearly six per cent in fuel consumption along the seven corridors was achieved. Furthermore, improvements in air quality were achieved. Volatile organic compounds were reduced by 3 per cent, nitrogen oxides by approximately 1 per cent, and carbon monoxide by nearly 1 per cent.

Economic analysis

Based on the results from the delay study, fuel consumption analysis, and the air quality analysis, an economic evaluation was conducted for the project to determine what benefits arose from the implementation of the new signal timing plans. The benefits studied included reduced road user costs from reduced delay experienced by the motoring public, air pollutants and fuel consumption. To determine these economic benefits, Kimley-Horn studied the AM, midday, and PM peak periods of the weekdays. Therefore, economic benefits were not quantified for the non-peak hours of the day and are not reflected in this analysis.

To calculate the cost savings resulting in the reduction of delay by the motoring public, a dollar value was assigned to the delay. The 324 US Department of Transportation provides data for this purpose. Using this data, analyses were made for each corridor in the project, and these results were tallied to yield a benefit in terms of reduced delay for the entire project. For a one-year period this benefit was calculated to be $14,770,900.

Economic benefits also were realised for the reduced emissions that resulted from the improved signal timing plans. This was calculated by assigning a cost to each of Economic analysis the three pollutants, as documented by the Federal Highways Administration. For the entire project over a one year period the benefit was found to be $33,655.

Similarly, the economic benefit was determined for the reduced fuel consumption. A conservative value of $2.00 per gallon of fuel was used for this analysis. For the whole project, this was found to be $637,630 for a one-year timeframe.

By using an engineering fee for this project, a benefit-to cost ratio was calculated. The benefits were the sum of the delay, emissions and fuel benefits over a one-year timeframe totaling $15,442,180. The cost was the contract value for the project: $750,000. This yielded a one year benefit-to-cost ratio of 21:1. However, the implemented signal timing plans will be used and prove to be beneficial for a time period longer than one year.

Typically the useful life for signal timing plans is three years, as recommended by the ITE ("At a minimum, an operating agency should budget to retime traffic signals at least every three years.") Therefore, the three-year benefit is $46,326,550, while the cost remains only $750,000. This yields a three-year benefit-to-cost ratio of 62:1.


RSS

Related Content

  • Techniques to improve fuel economy by 18.7% in public transit fleets
    April 2, 2012
    SmartDrive Systems, a specialist in fleet safety and operational efficiency, has announced the results of its Public Transit Fuel Efficiency Study, which reveals that transit fleets can reduce fuel consumption on average as much as 18.7 per cent, saving nearly US$3,400 per vehicle annually, by engaging in fuel-efficient, eco-driving best practices.
  • Cost Benefit: the economic case for cycling
    August 20, 2019
    Cycling is good for us for any number of reasons. David Crawford finds that it is now possible to access basic, low-cost data which will help make the economic case for improving infrastructure Cycling is enjoying a favourable press the world over as a ‘good thing’ in the economic, environmental and social spheres. A recent study on the Value of Cycling from the UK’s University of Birmingham, for example, shows that cycle-friendly urban settings can deliver annualised transport infrastructural support co
  • ITS industry in the US has grown to $48 billion and will expand
    April 17, 2012
    ITS America has released what it says is the most comprehensive study to date on the scope of the ITS industry in the United States and North America. Researchers found intelligent transportation to be a fast growing sector valued at approximately US$48 billion. Results indicate that cities and states with drastically reduced budgets are turning to technology solutions to maximize existing highway capacity.
  • Canadian authorities convinced of enforcement safety benefits
    November 28, 2012
    Cost-benefit analysis invariably finds highly in favour of speed and red light enforcement, particularly so in Edmonton in the Alberta province of Canada, where authorities need no convincing of the merits of road safety engineering. Justification of enforcement efforts on economic grounds has been reinforced this year, by a study of the costs and benefits of red light enforcement. New York-based economic research firm John Dunham & Associates carried out this latest analysis for American Traffic Solutions