Re-timing traffic signals delivers cost benefits

Nashville's signal optimisation programme produced a stunning return on investment. Are those results exceptional? Could similar results be replicated in cities across the US and indeed the world? ITS International spoke to Chris Rhodes, P.E. of Kimley-Horn and Associates, project leader for the Nashville signal optimisation programme. "You have to bear in mind that with signal optimisation programmes you don't see, for instance, physical construction or new pieces of equipment on the roadside that someone
June 28, 2012 Read time: 4 mins
Chris Rhodes, Kimley-Horn
RSS

Nashville's signal optimisation programme produced a stunning return on investment. Are those results exceptional? Could similar results be replicated in cities across the US and indeed the world? ITS International spoke to Chris Rhodes, P.E. of 422 Kimley-Horn and Associates, project leader for the Nashville signal optimisation programme.

To concentrate on the ROI (return on investment) dollar figures provided in the evaluation of the Nashville signal optimisation plan is slightly to miss the point of the exercise in the first place: to reduce congestion and improve travel times which also provide significant air quality and fuel consumption benefits.

However, it's worth noting that what was achieved in Nashville, from whatever viewpoint you take, was achieved without investment in new technology and through maximising the infrastructure that already existed. Or, as Kimley-Horn and Associates' Chris Rhodes, the project leader, puts it, "It was basically making the equipment they have work at its peak performance."

That's not because Nashville's equipment was out of date or deficient, in technology terms, in any way. As Rhodes points out, the ITE recommends that signals be retimed every three years as a matter of course.

Ask the question

So in terms of replicating Nashville's results, traffic managers, city and administration leaders in municipalities and cities anywhere in the world simply need to ask the question: when, if ever, did we last optimise our traffic signals? If the answer is six, nine, 12 or more years ago, then the kind of results achieved in Nashville will be fairly typical.

In Rhodes's experience, "People just don't do it as often as they should. Without generalising, a majority of administrations, for a variety of reasons, are simply not as proactive in undertaking this kind of programme as they should be."

But the effect of optimising just one section can be seen by the Nashville experience, as Rhodes explains: "The first phase Nashville asked us to undertake involved 223 signalised intersections along seven corridors. Funding came from the Federally funded CMAQ programme. Nashville was so impressed with the results, that they used their own budget to fund three more supplements, which we also did for them - totalling nearly 550 signals along a total of 29 corridors and the City's central business district.

"Now, Metro Nashville, under the Obama Administration's stimulus package, has requested another $1 million to go back and again retime the original seven corridors we did in 2004, because we are over that three-year window. So the Metro government is definitely sold on the benefits of signal retiming."

Strong argument

The evaluation report provided by Kimley-Horn and Associates for Nashville is certainly impressive and provides an extremely strong argument for undertaking such schemes. So, was that produced as some kind of sales brochure to win other contracts?

"Absolutely not," says Rhodes. "Producing this kind of report for this type of work is standard for Kimley-Horn. You have to bear in mind that with signal optimisation programmes you don't see, for instance, physical construction or new pieces of equipment on the roadside that someone can point to and say, 'that's what we spent the tax dollars on'. So you have to be able to document that the money you spent resulted in some sort of improvement and you need to quantify that."

As Rhodes points out, for signal timing, or indeed for ITS arterial signal systems where programmes are being designed, it is company policy to always go through a similar cost benefit evaluation analysis. Indeed, Rhodes is adamant that all such programmes should be factually and consistently documented.

Cost benefit basis

"I believe that these projects should be evaluated on a cost benefit basis," Rhodes says. "There is a way to do it because you can undertake very similar analyses using different types of data. On a freeway management system, for instance, you can document improvements in emergency response times for freeway incidents that can be directly attributed to CCTV camera feeds or speed detector data that allows operators to more quickly identify and effectively respond to freeway incidents. Evaluations are important for a variety of reasons, not least because the traffic engineers can take them to their leadership, the mayor, city council or other policyand decision-makers, and demonstrate that they spent money smartly and achieved tangible benefits.
RSS
UTC

Related Content

  • February 2, 2012
    Signal optimisation reduces congestion, improves travel times
    The Metropolitan Government of Nashville and Davidson County's Department of Public Works(MPW) identified seven corridors in the County that experience heavy traffic congestion and needed traffic signal timing improvements to improve traffic flow as well as air quality and fuel consumption. The seven corridors included a total of 223 signalised intersections. To conduct this study, termed the Traffic Signal Optimisation Study for the Metro Nashville Signal System, MPW received funding from the Federal Conge
  • January 30, 2012
    Is the US economic stimulus programme working?
    In this third installment in a series of articles exploring the impact of the US economic stimulus programme on the ITS industry, Pete Goldin reports on the ongoing debate in Congress about American Recovery and Reinvestment Act. A debate continues to rage in the US Congress and in the media about the effectiveness of the American Recovery and Reinvestment Act of 2009 (ARRA), and especially the timeliness of the ARRA payments. Some of the arguments seem somewhat partisan in origin while others point out fla
  • February 2, 2012
    Economic crisis needs non-partisan perspectives to stimulate growth
    Kary Witt, President of the IBTTA and Pat Jones, Executive Director and CEO, talk about the need to put aside partisan perspectives in order to deal with the current economic crisis
  • March 12, 2012
    Vendor's eye view of US economic stimulus programme
    Pete Goldin explores the impact of the US economic stimulus programme on the ITS industry from the ITS vendor perspective